Matter: Nova Scotia Power Inc. - CI C0059483 – 83V L-5017 and L-5046 Rebuild Tap - $1,558,116
1 passage 1 document

2026 DSM Extension across all matters →

1011952025 Q4 Capital Reports 1 passage
(3) Spending on projects started prior to 2025, not in the 2025 ACE Plan: Top 10 projects that were included in prior ACE Plans or approved prior to 2025
(3) Spending on projects started prior to 2025, not in the 2025 ACE Plan: Top 10 projects that were included in prior ACE Plans or approved prior to 2025 CI Project Title Functional Class 2025 Awaiting Approval Generation C0021608 TUC Shor...

AI summary The document lists the top 10 projects that were included in prior ACE Plans or approved prior to 2025, detailing their functional class, project title, and associated costs for 2025 and 2026. These projects are currently awaiting approval and are planned to be included in the 2026 ACE Plan.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →