on 5.1 allows for customersubmitted readings, NS Power still needs to receive, verify, and process these readings, along with handling disputes and correcting errors. [Exhibit N-8 Appendix 13A, p. 8] [675] In response to Board IR-148, NS P...
AI summary NS Power allows customer-submitted AMI readings but must verify, process, and resolve disputes. In 2024, 16 postcard and 161 photo meter submissions were received, though tracking accuracy is not done. Instructional materials are available online, with planned updates by 2026. NS Power can detect billing anomalies exceeding predefined thresholds.
3.10.2.1 Findings [680] The Board has several concerns with NS Power's request to implement AMI opt-out fees at this time. Based on the responses provided during the hearing, it appears that meter reader costs associated with opt-out meter...
AI summary The Board rejects NS Power's request to implement AMI opt-out fees, citing insufficient cost delineation, questionable forecasts (e.g., 20x increase in customer care costs), and reluctance to adopt self-reporting options for opt-out customers. NS Power's dismissal of self-reporting is challenged, as existing practices (e.g., accepting photo readings) contradict claims of feasibility issues. The Board directs NS Power to address these concerns in a compliance filing.
- In its next depreciation study, provide at minimum the following information in support of both production Plant and mass property: - o Detailed management notes for each account; - o All analysis and studies performed by management for...
AI summary The Nova Scotia Utility and Review Board directs NS Power to provide detailed depreciation study information, address cost-of-service concerns, revise climate adaptation plans, and use AMI data for rate adjustments. Key issues include IRP alignment, distribution cost allocation, OATT tariff applications, and customer charge settings.