HomeAffordabilityM12373Evidence
Topic/Matter Intersection

Topic:"Affordability" in M12373

Matter: Nova Scotia Power Inc. - CI C0067908 – POA Boiler Refractory Refurbishment 2025 – $1,378,466
1 passage 1 document

Affordability across all matters →

99231Board Decision Letter 1 passage
CI # C0067908 POA Boiler Refractory Refurbishment 2025 $1,378,466 p. pp. 0-2
CI # C0067908 POA Boiler Refractory Refurbishment 2025 $1,378,466 This capital item was included in NS Power's 2025 ACE Plan with a budget of $1,089,478, listed among the projects pending subsequent approval. In its submission, NS Power in...

AI summary NS Power requested approval for a $1.378 million refractory refurbishment project in 2025, citing increased material costs due to tariffs and market conditions. The Board accepted the project's necessity and approved the funding, noting NS Power's alignment with plant retirement plans and the critical role of refractory systems in boiler reliability.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →