CI # C0067908 POA Boiler Refractory Refurbishment 2025 $1,378,466 This capital item was included in NS Power's 2025 ACE Plan with a budget of $1,089,478, listed among the projects pending subsequent approval. In its submission, NS Power in...
AI summary NS Power requested approval for a $1.378 million refractory refurbishment project in 2025, citing increased material costs due to tariffs and market conditions. The Board accepted the project's necessity and approved the funding, noting NS Power's alignment with plant retirement plans and the critical role of refractory systems in boiler reliability.