Matter: To obtain a cost reasonableness review of NS Power - CI C0051815 – $5,959,515 - RTU Replacements Program – Phase 6, as outlined in Section 2.1 of the ACE 2025 decision (M12012)
3 passages 3 documents

Affordability across all matters →

N-3Evidence - Midgard - Redacted 1 passage
1 Table 18: Summary of Findings – Indirect Cost Allocation & Transparency p. p. 35
1 Table 18: Summary of Findings – Indirect Cost Allocation & Transparency Report Section Question Midgard Commentary 5.3 Are indirect cost components (including administrative overhead allocations, vehicle and travel loadings, and capitali...

AI summary The document discusses the transparency of indirect cost components, including administrative overhead, vehicle and travel loadings, and capitalized financing costs. It confirms that these components are calculated using transparent methodologies consistent with approved accounting policies, with measures such as a 50% reduction in overhead on overtime labour to minimize burden on ratepayers.

N-7Rebuttal Evidence - NS Power 1 passage
24 2.3 Use of Internal Resources
uld 28 not necessarily eliminate internal labour requirements, as internal technical presence and 29 coordination may still be required to supervise and support the work at site due to the familiarity DATE FILED: April 10, 2026 Page 9 of 2...

AI summary The document discusses the use of internal resources by NS Power, noting that even with external labor, internal oversight is required due to familiarity with systems and standards. It highlights increased labor and travel costs, suggesting inefficiencies and higher reliance on overtime and remote site logistics.

100750Letter NSPI re: RIRs and confidentiality 1 passage
1. Commercial Information p. p. 0
1. Commercial Information To protect value for customers and mitigate the risk of prospective proponents having access to the information itemized below, and maintain good business relations with vendors, this information is confidential....

AI summary NS Power seeks to keep supplier pricing and arrangement terms confidential to prevent competitors from gaining an advantage and to ensure the best terms for acquiring services and equipment. This confidentiality also benefits customers as rates are cost-based.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →