HomeAffordabilityM12596Evidence
Topic/Matter Intersection

Topic:"Affordability" in M12596

Matter: Nova Scotia Power Inc. - CI C0080228 – HYD Hollow Bridge Generator Refurbishment - $2,587,170 (U&U)
2 passages 2 documents

Affordability across all matters →

N-1Application - Redacted 1 passage
French: p. p. 21
French: Nonobstant toute disposition du bon de commande, des modalités et conditions ou de tout autre contrat, le client accepte que Wajax puisse augmenter le prix d'achat à tout moment avant la date de livraison pour refléter les suppléme...

AI summary The client agrees that Wajax may increase the purchase price at any time before delivery to account for additional costs, tariffs, or import duties imposed by any government authority, regardless of any terms or conditions in the contract.

100142Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
Commercial Information p. p. 0
Commercial Information Items 1-2: Partial confidentiality was applied to costs associated with materials, contracts, consulting, first nations commitments, and freight details provided in the capital work order(s). To protect value for cus...

AI summary NS Power argues for maintaining confidentiality of certain costs and supplier terms to protect customer interests and prevent competitive disadvantages. Transparency could allow competitors to gain an edge, leading to higher costs for customers. The confidentiality measure is intended to ensure NS Power can secure the most competitive terms for services and equipment.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →