HomeAffordabilityM12782Evidence
Topic/Matter Intersection

Topic:"Affordability" in M12782

Matter: Nova Scotia Power Inc. - Commercial Net Metering Program - 2025 Annual Report �
1 passage 1 document

Affordability across all matters →

101794NSEB (NSPI) IR-1 to IR-9 1 passage
Request IR-6:
Request IR-6: - a) Please confirm that the estimated value totals in Appendix A, Worksheet 2025 CNMP Summary, Cells G50 and L50 are the estimated annual value of sales offset by CNMP generation. Please clarify whether this is the amount of...

AI summary Request IR-6 seeks clarification on the estimated annual value of sales offset by CNMP generation, total avoided costs for behind-the-meter and grid-exported solar energy, and a comparison between avoided costs and incremental costs for exported energy.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →