7.0 COST & RIGHT OF WAY RESPONSIBILITY In accordance with NSPI Regulation 2.6, a load customer is responsible for providing the following: - a. A capital contribution for all line extension work in excess of 92m - i. If a line previously e...
AI summary The document outlines the responsibilities of load customers regarding cost and right-of-way (ROW) obligations under NSPI Regulation 2.6. Customers are responsible for capital contributions for line extensions beyond 92m, providing easements, and clearing ROWs. NSPI covers part of the costs for 3-phase line extensions, depending on the existing infrastructure. CBRH is specifically required to clear the ROW along Weatherbee Road.