Matter: Nova Scotia Power Inc. - CI C0053699 – Renewable to Retail Implementation - $5,644,468
2 passages 2 documents

Affordable Multifamily Housing And Non Profit Organizations Amf across all matters →

N-2NSPI (CA) RIR 1 to 4 1 passage
1 Request IR-1: p. p. 9
1 Request IR-1: 129 Ops 15 minute interval data must be provided for use in calculating peak demand for use in calculating the distribution tariff Peak demand data will be provided from MDMS derived from 15 minute interval data for use in...

AI summary The document outlines requirements for providing 15-minute interval data for distribution tariff calculations and details criteria for NS Power customers transferring to LRS, including financial obligations and hardware installation requirements. It also notes that customers leaving NS Power for LRS will lose eligibility for EV charging credits.

102536Decision 1 passage
3.2.1 Cost Transparency p. p. 17
3.2.1 Cost Transparency [46] In closing submissions, the Small Business Advocate noted that the costs identified in this application represented a $581,816 increase from the estimated cost that NS Power included in its 2025 ACE Plan. The S...

AI summary The Small Business Advocate highlights a $581,816 increase in costs from the 2025 ACE Plan, noting NS Power's inability to reconcile the changes. NS Power attributes the increase to project delays and administrative overhead, while the Advocate recommends standardized reporting for cost impacts. NS Power provided year-by-year cost details but not driver-level estimates.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →