2.2 Impact of Cybersecurity Incident on Project AFUDC Costs - The CA raises further concerns regarding the AFUDC included in NS Power's application and - recommends that the Board disallow a portion of these costs. This position is based o...
AI summary The CA recommends disallowing a portion of AFUDC costs for NS Power's IAM project due to a 12-month delay attributed to insufficient internal resources, potentially linked to a cybersecurity incident. NS Power disagrees, stating the delay was due to changes in project scope, the NIST Cybersecurity Framework, and evolving technology, not the incident itself.