98001Letter IG re: Extension request 1 passage
Section 1 p. p. 0
File Reference: SM002557.00003 Nancy G. Rubin, K.C. Direct Dial: 902.420.3337 [email protected] June 11, 2025 Via Electronic Mail Ms. Crystal Henwood Regulatory Affairs Officer/Clerk Nova Scotia Energy Board 1601 Lower Water Stree...

AI summary The Industrial Group requests an extension until June 16, 2025, to submit Information Requests (IRs) for Matter M12282, citing consultant time constraints. E1's counsel agrees to the extension.

99112Email NSEB re: Extension approved for IG to provide hearing logistics 2 passages
Preamble p. p. 0
From: [Henwood, Crystal D](mailto:[email protected]) To: [Nancy G Rubin;](mailto:[email protected]) [Alice Napoleon](mailto:[email protected]); [Allison Coffin](mailto:[email protected]); [Angela Co...

AI summary The Board has approved an extension until August 29, 2025, for the M12282-E1 proceeding related to a new BCA Test for Demand Side Management (DSM). The email is addressed to multiple stakeholders, including legal and energy consulting professionals.

\ \ EXTERNAL EMAIL / COURRIEL EXTERNE \ \ p. p. 0
\ \ EXTERNAL EMAIL / COURRIEL EXTERNE \ \ Exercise caution when opening attachments or clicking on links / Faites preuve de prudence si vous ouvrez une pièce jointe ou cliquez sur un lien Good morning, Ms. Henwood, I will be appearing as c...

AI summary Nancy Rubin, counsel for the Industrial Group, along with Brianne Rudderham, is preparing for proceedings involving expert Patrick Bowman. They seek an extension to decide on virtual appearance after cross-examination.

99131E-mail IG re: Hearing Logistics 2 passages
This is an external email. p. p. 1
This is an external email. Ms. Rubin, Further to your email below, the Board approves your extension request until 2:00 PM on Friday, August 29, 2025. Regards,

AI summary The Board approves an extension request until 2:00 PM on Friday, August 29, 2025, in response to an email from Ms. Rubin. The approval is communicated via an external email.

\ \ EXTERNAL EMAIL / COURRIEL EXTERNE \ \ p. p. 1
\ \ EXTERNAL EMAIL / COURRIEL EXTERNE \ \ Exercise caution when opening attachments or clicking on links / Faites preuve de prudence si vous ouvrez une pièce jointe ou cliquez sur un lien Good morning, Ms. Henwood, I will be appearing as c...

AI summary Nancy Rubin, counsel for the Industrial Group, informs Crystal Henwood of appearing with Brianne Rudderham and expert Patrick Bowman. They seek time to decide if Bowman may testify virtually after cross-examination, requesting a brief extension.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →