Preamble p. p. 0
Appeal - NS Power Dispute Resolution Officer (DRO) Reference Number: 260310001 Submitted on: Tuesday, March 10 2026 at 11:31:10 AM (ADT) Contact Information Name on account: Emily Martin Account number: Business contact: Account address: A...

AI summary An appeal referencing NS Power's Dispute Resolution Officer (DRO) decision is submitted by Emily Martin on March 10, 2026. The document includes contact details and a reference number (260310001) for the proceeding, though specific arguments or claims are not detailed in the provided text.

M-9DRO Decision d. March 10, 2026 (redacted) 1 passage
Emily Martin p. p. 0
ll period even though there was a meter reading error. (100 + 1400 1000 + 500). The same effect occurs if the meter reading is estimated, or erroneously reported, either higher or lower than the fact. Your dispute is in part a "consumption...

AI summary The Dispute Resolution Officer (DRO) rules that Nova Scotia Power (NSP) correctly billed the customer for on-premise energy consumption, as the meter was found accurate within prescribed limits. NSP's responsibility is to deliver power to the meter, not control consumption. The customer may appeal to the Nova Scotia Energy Board (NSEB) or consult Efficiency Nova Scotia for consumption advice.

M-10NSPI Response to Appeal (redacted) 2 passages
REDACTED p. p. 0
REDACTED Lisa Wallace Chief Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: M12737 – DRO Appeal – Emily Martin Dear Ms. Wallace: On March 10, 2026 Ms. Emily Martin filed an Appeal of a...

AI summary Emily Martin appeals a DRO decision regarding her electricity billing. The Nova Scotia Energy Board directed NS Power to respond by March 25, 2026, with attachments including the DRO file, invoices, and meter data. The appeal concerns billing discrepancies and requires a formal response from the utility.

Procedural Background p. p. 0
Procedural Background Please accept the following summary of activities and communications pertaining to the March 10, 2026 DRO decision being appealed by Emily Martin. • February 17, 2026 – Ms. Martin emailed the DRO to dispute her Decemb...

AI summary Emily Martin appealed a March 10, 2026 DRO decision regarding her February 2026 energy bill, disputing the $1,865.48 charge for 9,483 kWh usage. She claimed NS Power failed to provide evidence of her consumption, noting she installed a heat pump in 2023. The DRO requested account details from NS Power, which complied, providing ledger and meter data.

M-11MARTIN (NSEB) RIR-1 to RIR-3 (redacted) 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPEAL OF THE DISPUTE RESOLUTION OFFICER'S DECISION by a customer of NOVA SCOTIA POWER INC. (NS Power) - Emily Martin

AI summary The Nova Scotia Energy Board is considering an appeal by Emily Martin, a customer of Nova Scotia Power Inc., against a decision by the Dispute Resolution Officer under the Public Utilities Act.

101189Board Acknowledgment Letter (redacted) 2 passages
Section 1 p. p. 0
March 11, 2026 Emily Martin Dear Appellant: M12737 – Nova Scotia Power Inc. – Appeal by Emily MARTIN of a Decision of the Dispute Resolution Officer This will acknowledge receipt of your correspondence received by the Board on March 10, 20...

AI summary The Board acknowledges Emily Martin's appeal against a Nova Scotia Power Inc. (NS Power) Dispute Resolution Officer decision. NS Power must respond by March 25, 2026, and provide the complete DRO file. The Board emphasizes that appeals do not halt arrears recovery actions by NS Power, and evidence submitted will be public unless confidential status is requested under Regulatory Rule 12.

Section 2 p. pp. 0-1
file reviewed by the DRO in reaching its decision, including any supporting information and comments NS Power wishes the Board to consider. NS Power must also provide a copy of their response to you. As the appellant, you will have 10 busi...

AI summary The Board outlines procedural steps for an appeal, including NS Power's submission requirements, the appellant's 10-day response window, and a directive to suspend disconnection notices pending the Board's decision. Contact information for the Chief Clerk is provided.

102012NSEB (MARTIN) IR-1 to IR-3 (redacted) 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPEAL OF THE DISPUTE RESOLUTION OFFICER'S DECISION by a customer of NOVA SCOTIA POWER INC. (NS Power) – Emily Martin

AI summary The Nova Scotia Energy Board is handling an appeal under the Public Utilities Act, involving Emily Martin and Nova Scotia Power Inc. (NS Power), challenging a Dispute Resolution Officer's decision. The proceeding centers on regulatory oversight and customer disputes related to utility services.

102013NSEB (NSPI) IR-1 to IR-4 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPEAL OF THE DISPUTE RESOLUTION OFFICER'S DECISION by a customer of NOVA SCOTIA POWER INC. (NS Power) – Emily Martin

AI summary The Nova Scotia Energy Board is handling an appeal under the Public Utilities Act by Emily Martin, a customer of Nova Scotia Power Inc. (NS Power), challenging the Dispute Resolution Officer's decision.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →