1 Request IR-6:
Historical Projects 2017-2021 1 Request IR-6: 15 increased efficiency in the delivery of cost-effective electricity for customers. 16 17 (b) NS Power does not track this information. NS Power's capital projects are justified in 18 accordan...

AI summary The document discusses NS Power's capital projects and efficiency initiatives from 2017 to 2021, noting that NS Power does not track energy, demand, and cost savings from these activities. It also mentions that efficiency projects are included in the ACE Plan and capital approval applications.

85904Notice of Intervention - NRR 1 passage
To: Nova Scotia Utility and Review Board
To: Nova Scotia Utility and Review Board - 1. NRR intends to participate in this proceeding. - 2. Through the Minister of Natural Resources and Renewables, NRR has the supervision, direction and control of all matters relating to energy re...

AI summary NRR intends to participate in the proceeding and outlines its role in energy policy, resource management, and administration of energy-related legislation in Nova Scotia.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →