Matter: EfficiencyOne - 2026 DSM Extension ApplicationIN THE MATTER OF An Application by EfficiencyOne for Approval of the 2026 DSM Extension for Demand-Side Management Activities between EfficiencyOne and Nova Scotia Power Inc., and for Approval of the Amendment to the 2023-2025 Demand-Side Management Purchase Agreement between EfficiencyOne and Nova Scotia Power Inc.
3 passages 3 documents

Asset Management across all matters →

E-2Savings Verification Review - Gil Peach 1 passage
K. BNI Custom Incentives Program (Custom Component) p. pp. 70-71
- (b) Leakage rate has increased. There has been an unexplained recent surge in claimed savings at these two locations, as compared to prior years. This surge should be examined by the Evaluator and explained. Our expectation is that, over...

AI summary The text highlights concerns about increased leakage rates and unexplained savings surges in a program, questioning maintenance practices and proprietary data policies. It argues that facilities should have incorporated leak detection standards and that evaluation requires access to non-proprietary data. The Evaluator is tasked with reviewing policies and explaining discrepancies.

E-14Peach (E1) RIR 1 to 14 - Redacted 1 passage
5 Response IR-06: p. p. 12
ually comes down to decision making about infrastructure and the resource plan. System planning engineers and executive management will have a sound perspective on what makes sense and what does not.

AI summary The text emphasizes that decision-making regarding infrastructure and resource planning relies on the expertise of system planning engineers and executive management to evaluate feasible options. It highlights the importance of their perspective in determining viable solutions.

E-17Reply Evidence- E1 including Appendix A -Econoler Reply Evidence 1 passage
4. Maintenance Issue p. pp. 43-44
4. Maintenance Issue The Peach Report states as follows in relation to the customer's lack of ongoing maintenance of compressed air leaks: [41](#page-44-2) It is not clear why an organization with multiple similar sites located worldwide w...

AI summary The Peach Report criticizes the customer's failure to maintain compressed air leaks, suggesting that corporate policies and existing standards should have addressed the issue without ongoing DSM funding. It references successful integration of practices in other DSM programs and corporate sectors, emphasizing the need for evaluators to review client policies.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →