Request IR-3:
Request IR-3: - a) Is the 400 metres section of main estimated to be replace the full length of the distribution main on Bennies Lane and Bennies Lane Extension? - i. If not, why was this section of the lane chosen to be replaced? - ii. If...
AI summary Request IR-3 seeks clarification on the replacement of a 400-metre section of the distribution main on Bennies Lane and Extension. It questions whether this section represents the full replacement scope, the rationale for selecting this segment, future plans for the remaining main, and the proposed timeline for any additional work.