6.04.01 Forecasting Annual Joint Use Budget Requirements Using the appropriate forecasting forms, each party to this Agreement must identify all planned Joint Use Construction for the coming budget year. MT&T personnel will use Forms A and...
AI summary This section outlines the process for forecasting annual joint use budget requirements, specifying that each party must identify planned joint use construction using designated forms. MT&T and NSPI personnel are assigned different forms for this purpose.
6.04.02 Forecasting Procedure - On or before July 1 of each year, the Joint Use Coordinators will issue the appropriate Joint Use Forecasting forms to the MT&T District OPE Supervisor/ NSPI Zone Manager for completion. - The forecast shall...
AI summary This section outlines the forecasting procedure for joint use requirements, detailing the timeline, responsibilities of Joint Use Coordinators and MT&T District OPE Supervisor/NSPI Zone Manager, and the process for reviewing and addressing forecasted requirements.