N-1Application - CI C0030984 - IT - Cisco UCS Lifecycle FIN 1 passage
Reason for Variance - FIN p. p. 1
Reason for Variance - FIN This project was underspent by $367,611 compared to the approved budget of $2,456,609 for a total of $2,088,998. The variance is primarily driven by un-utilized contingency. Additionally, less internal labour was...

AI summary The project was underspent by $367,611 due to un-utilized contingency and lower internal labour costs than originally budgeted, resulting in a total expenditure of $2,088,998.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →