Matter: CI# 38878 - P-128.10 - NSPI WO - 2010 Substation Cutout and Insulator Replacements - $1,506,414
1 passage 1 document

Capacity Costs across all matters →

N-1Redacted Work Order 9/2/2010 1 passage
p. p. 1
POWER An Emera Company ? UARB APPRO VAL SHEET 2010 1,500,961 1,506,414 Estimated Start Date 2010-10

AI summary The document presents a table with information related to a project, including the year 2010, a value of 1,500,961, another value of 1,506,414, and an estimated start date of 2010-10. The table includes columns such as 'POWER An Emera Company', 'UARB APPRO', 'VAL SHEET', and others.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →