06618Board Decision 3/21/2011
4 passages
III NSPI PROPOSED AMENDMENTS [12] In its Application, NSPI proposed the following amendments to Regulation 3.6: - a) Increase the existing limit for customer generating capacity from 100 kW to 1 MW. - b) Increase the existing net metering...
AI summary NSPI proposed amendments to Regulation 3.6, including increasing customer generating capacity limits, reclassifying net metering customers, expanding meter aggregation, and revising surplus generation compensation. The proposal was discussed with the NSDOE and stakeholders to ensure alignment with the amended Electricity Act.
IV SUBMISSIONS BY INTERESTED PARTIES and NSPI's RESPONSE [15] Although seven parties registered as participants in this proceeding, only one party, HRWC, in addition to Board Counsel consultant, Multeese, submitted Information Requests or...
AI summary Only HRWC and Board Counsel Multeese submitted information requests or written submissions in the proceeding. HRWC's submission addressed three key issues: the definition of a 'distribution zone,' maximum generation capacity limits for net metering installations, and the assignment of environmental credits to NSPI.
2. Capacity Limits [23] HRWC's position regarding the net metering capacity limit is as follows: ... a cap of 20MW (about 1% of maximum NSPI system demand) appears overly restrictive, and there has been no evidence provided by NSPI to sugg...
AI summary HRWC argues that the 20 MW net metering capacity limit imposed by NSPI is overly restrictive and lacks sufficient evidence. NSPI defends the cap as an increase from the current 12 MW limit and suggests it will allow monitoring of cost recovery implications. Both parties agree on the need for future review once the limit is reached.
2. Capacity limits [38] The amended Electricity Act states that the net metering program \;vill permit any customer to generate electricity for the customer's own use and to sell any excess electricity to the utility. It also states that t...
AI summary The amended Electricity Act allows net metering up to 1 MW per customer without an overall system limit. NSPI proposed a 20 MW system limit divided into two classes, but the Board does not support this limit, emphasizing the need to encourage renewable energy participation. The Board, however, agrees with classifying generators into two categories to facilitate interconnection.
06618Board Decision 3/21/2011
4 passages
III NSPI PROPOSED AMENDMENTS [12] In its Application, NSPI proposed the following amendments to Regulation 3.6: - a) Increase the existing limit for customer generating capacity from 100 kW to 1 MW. - b) Increase the existing net metering...
AI summary NSPI proposed amendments to Regulation 3.6, including increasing customer generating capacity limits, revising net metering program capacities, establishing two classes of service, expanding meter aggregation, and modifying surplus generation compensation. The amendments aim to align with interconnection standards and facilitate administrative processes. NSPI also confirmed alignment with the Electricity Act and engaged stakeholders in the process.
IV SUBMISSIONS BY INTERESTED PARTIES and NSPI's RESPONSE [15] Although seven parties registered as participants in this proceeding, only one party, HRWC, in addition to Board Counsel consultant, Multeese, submitted Information Requests or...
AI summary In this proceeding, only HRWC and Board Counsel consultant Multeese submitted information requests or written submissions. HRWC's submission focused on three issues: the definition of a 'distribution zone,' maximum generation capacity limits for net metering installations, and the assignment of environmental credits to NSPI.
2. Capacity Limits [23] HRWC's position regarding the net metering capacity limit is as follows: ... a cap of 20MW (about 1% of maximum NSPI system demand) appears overly restrictive, and there has been no evidence provided by NSPI to sugg...
AI summary HRWC argues that the 20 MW net metering capacity limit imposed by NSPI is overly restrictive and lacks sufficient evidence. NSPI defends the cap, citing its increase from 12 MW and the need to monitor cost recovery implications. NSPI also plans to revisit the cap in the future and agrees with a recommendation to adjust the Class 2 limit to 101 kW.
2. Capacity limits [38] The amended Electricity Act states that the net metering program \;vill permit any customer to generate electricity for the customer's own use and to sell any excess electricity to the utility. It also states that t...
AI summary The amended Electricity Act allows net metering up to one megawatt per customer, with no overall system limit. NSPI proposed a 20 MW system limit divided into two classes, but the Board does not support imposing such limits without evidence, emphasizing the importance of distribution zone capacity and ongoing monitoring.