HomeCapacity CostsM09096Evidence
Topic/Matter Intersection

Topic:"Capacity Costs" in M09096

Matter: Approval of a Supply Agreement for Electricity Efficiency and Conservation Activities between EfficiencyOne (E1) and Nova Scotia Power Inc.(NS Power), the establishment of a final agreement between the parties, and approval of a 2020-2022 Demand Side Management (DSM) Resource Plan
14 passages 10 documents

Capacity Costs across all matters →

E-1-1Application 1 passage
Avoided Cost Category Unit Value Source p. pp. 193-194
Avoided Cost Category Unit Value Source Capacity $/MW 195,990 2014 IRP, Base DSM scenario (levelized over 2020-2035) Transmission $/MW Starts at 10,521 in 2018 Provided by NS Power in 2018; assumed to escalate at 2% per year Distribution $...

AI summary The table presents avoided costs for various categories such as capacity, transmission, distribution, and energy, with values and sources provided. The section titled '3.6 PROGRAMS' indicates the start of a discussion on programs, likely related to energy efficiency or demand-side management.

E-3E1 (NSPI) RIRs to IR-1 to IR-69 4 passages
Section 410
$11,911,927 Newmarket-Tay Power Distribution Ltd. 36.2 $9,649,555 Niagara Peninsula Energy Inc. 74.4 $19,056,865 Niagara-on-the-Lake Hydro Inc. 11.7 $2,993,633 Norfolk Power Distribution Inc. 18.9 $5,056,939 North Bay Hydro Distribution Li...

AI summary The document lists various power distribution companies along with their respective capacities and associated costs. These figures provide an overview of the distribution infrastructure and financial commitments across different regions.

Section 1547
ement for Electricity Efficiency and Conservation Activities between E1 and Nova Scotia Power Inc. (DSM 2020- 2022) M09096 (E-ENS-R-19) E1 Responses to Nova Scotia Power Inc. (NS Power) NON-CONFIDENTIAL 1 Request IR-39: 2 3 Reference: Evid...

AI summary EfficiencyOne explains that demand reduction provides long-term benefits to ratepayers by avoiding mid and long-term capacity issues, even though it does not yield direct energy savings. The response outlines incremental demand reductions for 2020, 2021, and 2022 and addresses the calculation of capacity savings and avoided costs.

Section 1551
component was modelled as one discrete measure having both energy and capacity related 21 avoided costs with a NPV of $140, 663,694. 22 23 d) No such conversion was necessary – the demand focused measures and activities proposed 24 to be i...

AI summary The text discusses the modelling of a component with energy and capacity-related avoided costs, valued at $140,663,694 in NPV. It highlights that demand-focused measures will provide capacity savings starting in 2020 and continuing until the end of their Effective Useful Lives, offering both short-term and mid-to-long term demand savings.

Section 1680
]) New: EL (=20 years, Operating Hours taken from Table 2.0.0 page 233 [3]), no source listed GDS Associates, Inc. Appendix C Page C-8 Date Filed: March 29, 2019 NS Power IR-41 Attachment 1 Page 25 of 36

AI summary The text references a 20-year period with operating hours derived from Table 2.0.0, page 233, and mentions GDS Associates, Inc. in the context of a document filed on March 29, 2019, related to NS Power's IR-41 Attachment 1.

E-52018 DSM Evaluation Reports 1 passage
Capacity p. p. 21
Capacity With the information available in the tracking sheet, the retired unit average capacity was established at 5,905 Btu/hr.

AI summary The retired unit average capacity was established at 5,905 Btu/hr based on the information available in the tracking sheet.

E-12E1 (EAC) RIR-1 to RIR-14 1 passage
16 Table 1: Other Resource Impact Values p. p. 0
16 Table 1: Other Resource Impact Values Impact Type Units Value Water $/m3 0.51 Fuel Oil $/liter 0.78 Wood $/cord 300 Pellet $/tonne 300 Year 2019 2020 2021 2022 2023 2024 Avoided Costs of Energy ($/kWh) 0.057 0.060 0.062 0.084 0.085 0.08...

AI summary Table 1 presents resource impact values for water, fuel oil, wood, and pellets, along with avoided costs for energy, capacity, and transmission from 2019 to 2042. EfficiencyOne (E1) responded to the Ecology Action Centre (EAC).

E-17E1 (SBA) RIR-1 to RIR-49 1 passage
Date Filed: May 13, 2019 E1 (SBA) IR-13 Page 3 of 3 p. p. 276
Date Filed: May 13, 2019 E1 (SBA) IR-13 Page 3 of 3 Sector Avoided Cost Savings Types 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Residential Energy Savings (kWh) $0.24 $0.24 $0.25 $0.25 $0.26 Residential Coinc. Demand Savi...

AI summary The document presents a table detailing avoided cost savings across different sectors and years, including energy savings, demand savings, and costs related to capacity, transmission, and distribution for residential and BNI sectors from 2020 to 2031.

E-18E1 (Synapse) RIR-1 to RIR-47 1 passage
Initial Estimate of T&D Avoided Costs p. pp. 69-70
Initial Estimate of T&D Avoided Costs ACE Plans[1](#page-70-0) and associated Board decisions for the past eight years were utilized to determine which Transmission and Distribution (T&D) capital investments were related to load growth, as...

AI summary The document outlines the methodology used to estimate T&D avoided costs, focusing on load growth-related investments from 2008 to 2015. It references ACE Plans and Board decisions, and provides initial estimates of T&D costs per MW for transmission and distribution.

E-20NSPI (CA) RIR1 to RIR-54 - Redacted 2 passages
NON-CONFIDENTIAL p. p. 60
NON-CONFIDENTIAL 1 Response IR-39: 2 3 From Richard Levitan, Levitan & Associates, Inc.: 4 5 (a) These claimed benefits refer to peak demand reduction and avoided capacity costs. 6 7 (b) The results of the 2019 pilots will provide the basi...

AI summary The response from Richard Levitan discusses the limitations of using 2019 DSM pilot results to estimate peak demand reduction and avoided capacity costs. It argues that the results of these pilots will help reduce uncertainties but will not fully resolve them, and that a linear extrapolation of 2019 data to estimate 2020-2022 results is premature and may be inaccurate.

2020-2022 Demand Side Management (DSM) Resource Plan (NSUARB M09096) NSPI Responses to Consumer Advocate Information Requests p. p. 60
2020-2022 Demand Side Management (DSM) Resource Plan (NSUARB M09096) NSPI Responses to Consumer Advocate Information Requests 1 Request IR-40: 2 • Minimum of 157 to 171 MW of 10-Minute Reserve (based on the net rating of the 3 largest onli...

AI summary The document discusses NSPI's responses to information requests regarding reserve requirements and capacity avoidance uncertainties in the 2020-2022 DSM Resource Plan. It highlights the reserve margins required by NS Power and mentions uncertainty around avoided capacity costs.

E-21NSPI (EAC) RIR-1 to RIR-7 1 passage
Table 1. Summary Avoided Energy and Capacity Costs – 2018‐2042 p. p. 3
Table 1. Summary Avoided Energy and Capacity Costs – 2018‐2042 ntia l Re ere Req uire (W nts ven ue me hol le) esa Bas is Sc 1 acit late d cap y re Ref s $0 00 cost $73, 630 $81, 885 $109 ,448 $114 ,237 $12 6,04 0 $ 175,5 02 $18 5,20 3 $ 1...

AI summary Table 1 summarizes avoided energy and capacity costs from 2018 to 2042, comparing different scenarios. It provides a detailed breakdown of costs associated with various demand-side management and capacity-related strategies over time.

E-23NSPI (IG) RIR-1 to RIR-10 - Redacted 1 passage
NON-CONFIDENTIAL p. p. 12
NON-CONFIDENTIAL 1 Request IR-2: 2 3 Reference: At page 8, NSPI states, it "is not currently forecasting further capacity 4 additions in the near to mid term." 5 6 What time period is this referencing? 7 8 Response IR-2: 9 10 NS Power does...

AI summary NSPI states it is not forecasting further capacity additions in the near to mid term. The response clarifies that no additional capacity is anticipated for at least the next 10 years, as assessed in the Load Forecast and 10 Year System Outlook reports.

77430Synapse (NSPI) IR-1 to IR-41 1 passage
1 Page 33 of Refer to NS Power's evidence, which states: "As proposed by NS Power Request IR-18:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 a. To what extent-in both percentage and absolute values-does the incorporation of customer-related costs distort the allocation of benefits an...

AI summary The document includes several requests for information related to NS Power's evidence, including the exclusion of customer-related costs, the calculation of avoided marginal costs, the use of levelized fuel costs, and the impact of DSM on thermal generation capacity factors. These requests aim to clarify the assumptions and data behind NS Power's analyses.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →