Request IR-8: 1 3 4 5 6 7 8 9 10 11 12 13 14 15 2 At Page 2 of 2 of the NSPI (NSUARB) IR-140 (Exhibit N-9 of 2025 ACE Plan), NS Power states: The increase in estimated labour hours for Phase 6 in comparison to Phase 1 is a direct result of...
AI summary The document discusses the increase in estimated labour hours for Phase 6 compared to Phase 1, attributing it to factors such as infrastructure complexity, compliance changes, accessibility, technology, and workforce constraints. It requests NS Power to provide average hours per RTU for each job title in both phases.
At Page 2 of 2 of the NSPI (NSUARB) IR-140 (Exhibit N-9 of 2025 ACE Plan), NS Power also states: Regular Labour (Internal) Unit Days Total Hours Avg Hours per RTU T & D Labor (Engineering & Technicians) PD 485 3880 485 Preamble: In Underta...
AI summary NS Power highlights challenges with accessibility and workforce constraints that necessitate overtime for RTU installations. However, the Phase 6 capital project budget only explicitly allocates overtime for SM Electricians, with a limited allowance of 20 person-days for the entire project.