N-1Application
2 passages
Contingency Statement Contingency for this project has been determined using a combination of internal subject matter expertise (Project Managers, Engineers and System Operators) experience gained from similar software development/implemen...
AI summary The contingency for the project is set at 10 percent, classified as a Class 1 estimate. This accounts for risks arising from the integration of new technology with legacy systems, based on internal expertise and non-binding guidelines.
This project is being submitted as a Class 1 estimate. The defined deliverables of this project indicate that 100% of the Class 1 deliverables have been defined/completed towards the Class Estimate. A contingency value of 10% was selected...
AI summary The project is submitted as a Class 1 estimate with 100% of deliverables defined. A 10% contingency was included to address risks from integrating new technology with legacy systems.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →