Section 17
p. p. 5
This project is being filed as a Class 3 estimate. The define deliverables for this project indicate that 52% of Class 3 deliverables have been completed. A contingency value of 15% was selected to account for specific risks such as weathe...
AI summary The project is being submitted as a Class 3 estimate with 52% of deliverables completed. A 15% contingency has been allocated to address risks including weather, cable repairs, archaeological findings, and marine mobilization.