This project is being filed as a Class 3 estimate. The defined deliverables for this project indicate that 81% of Class 3 deliverables are completed. A contingency value of 15% was selected to account for specific risks such as additional...
AI summary The project is filed as a Class 3 estimate with 81% of deliverables completed. A 15% contingency is included for risks like overtime, contract cost increases, and access to structures at two water crossings. Construction has not yet begun.