HomeCapacity CostsM12960Evidence
Topic/Matter Intersection

Topic:"Capacity Costs" in M12960

Matter: Nova Scotia Power Inc. - CI C0052654 – L5541 Water Crossing Upgrades - $2,265,295 (ATO)
2 passages 2 documents

Capacity Costs across all matters →

N-1CI C0052654 – L5541 Water Crossing Upgrades - $2,265,295 1 passage
Preamble p. p. 6
This project is being filed as a Class 3 estimate. The defined deliverables for this project indicate that 81% of Class 3 deliverables are completed. A contingency value of 15% was selected to account for specific risks such as additional...

AI summary The project is filed as a Class 3 estimate with 81% of deliverables completed. A 15% contingency is included for risks like overtime, contract cost increases, and access to structures at two water crossings. Construction has not yet begun.

102745Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
2026 ACE Plan Capital Items for Subsequent Approval p. p. 0
2026 ACE Plan Capital Items for Subsequent Approval • CI C0082195 – LIN2 2025/26 Capacity Requirement - $4,392,251 2026 ACE amount $ 3,162,203 $4,392,251 spent as at March 31, 2026 Non-Confidential

AI summary The document outlines the 2026 ACE Plan Capital Items for Subsequent Approval, including the LIN2 2025/26 Capacity Requirement with a total cost of $4,392,251 and an approved amount of $3,162,203 as of March 31, 2026.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →