Matter: Nova Scotia Power Inc. - CI C0068659 – TRE5 – IP-LP Turbine Refurbishment - $2,963,160 (ATO)
1 passage 1 document

Capacity Costs across all matters →

N-1CI C0068659 – TRE5 – IP-LP Turbine Refurbishment - $2,963,160 1 passage
Reason for Variance - ATO p. p. 3
Reason for Variance - ATO The increase of $1,680,490 over the approved 2025 ACE Plan budget of $1,282,670 is due to additional conditionbased work identified only after disassembly. The original project estimate was developed with the supp...

AI summary The increase in the 2025 ACE Plan budget by $1,680,490 is due to unexpected defects found during the turbine disassembly and refurbishment process, leading to additional costs for repairs and inspections. These costs were necessary to ensure the turbine's safe and proper operation.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →