Reason for Variance - ATO
p. p. 3
Reason for Variance - ATO The increase of $1,680,490 over the approved 2025 ACE Plan budget of $1,282,670 is due to additional conditionbased work identified only after disassembly. The original project estimate was developed with the supp...
AI summary The increase in the 2025 ACE Plan budget by $1,680,490 is due to unexpected defects found during the turbine disassembly and refurbishment process, leading to additional costs for repairs and inspections. These costs were necessary to ensure the turbine's safe and proper operation.