Contingency Statement Contingency for this project has been determined using a combination of internal subject matter expert (Professional Engineers) judgment, previous experience with hydro unit overhaul projects, as well as the non-bindi...
AI summary The contingency for the project is set at 20 percent, determined using internal expertise, previous experience, and non-binding guidelines. It covers water management risks, potential refurbishments, and unforeseen increases in material and contract costs.
Document No: XXX-XX-XXXX-XXXX Project Cost Estimate Input Checklist and Maturity Matrix Hydropower Required fields: Estimate Classification Project Name: HYD TUS 1 Overhaul Started or Preliminary Class 5 Class 4 Class 3 Class 2 Class 1 Mat...
AI summary This document outlines a project cost estimate input checklist and maturity matrix for the HYD TUS 1 Overhaul hydropower project. It details the project's scope, capacity, location, requirements, technology selection, strategy, and planning, with various levels of definition and maturity.