Topic/Matter Intersection

Topic:"Capacity Market Participation" in M03415

Matter: NSPI CI# 38819 - $7,452,511 - 51V Tremont Circuit Breaker & Bus
4 passages 2 documents

Capacity Market Participation across all matters →

N-1Redacted Work Order 3 passages
Why do this project now? p. p. 7
Why do this project now? The 2010/11 peak load on the 69kV system in the Annapolis Valley is forecasted to reach levels such that failure of some source elements (138kV line or 138-69kV transformer) during peak load conditions causes the v...

AI summary The 2010/11 peak load on the 69kV system in the Annapolis Valley is expected to reach levels where the failure of certain components could lead to voltage drops and potential outages.

Consulting – Design $386,500 p. p. 7
Consulting – Design $386,500 This estimate includes costs for protection and control design, substation design, and witnessing of tests.

AI summary The document outlines a consulting design cost of $386,500, which covers protection and control design, substation design, and test witnessing.

7 Table 3 Breakdown of CI#11004 Canaan Rd. Circuit Breaker Additions p. pp. 7-19
7 Table 3 Breakdown of CI#11004 Canaan Rd. Circuit Breaker Additions Account 2010 Total 2011 Total Project Total Labour 161,831 0 161,831 Overtime Labour 7,420 0 7,420 Materials Contracts Other 24,893 0 24,893 Interest 29,521 0 29,521 AO 2...

AI summary The text discusses the breakdown of costs for the Canaan Rd. Circuit Breaker Additions project, including labor, materials, and interest, and outlines NSPI's plans for completing design and electrical work at the Canaan Road and Tremont Substations. It emphasizes the confidentiality of the study and material information due to system security concerns and competitive advantage considerations.

06178Board Decision and Order 1 passage
ORDER
ORDER WHEREAS Nova Scotia Power Incorporated ("NSPI") filed applications on July 27, 2010, with the Nova Scotia Utility and Review Board (the "Board") for approval of Work Orders CI# 38819 - 51V Tremont Circuit Breaker & Bus in the amount...

AI summary The Nova Scotia Utility and Review Board approved NSPI's applications for work orders related to electrical infrastructure upgrades, including transmission lines and circuit breaker additions, after considering stakeholder input and reviewing the affiliate transaction with Emera Utility Services.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →