B-11Evidence of Alliance of Nova Scotia Sawmillers 3/22/2011
6 passages
II. Overview and General Issues - Q. Are you proposing flat COMFIT rates or variable rates? - A. We are commenting strictly on technical and budgetary considerations. Rates will be addressed under separate testimony by ANSS.
AI summary The document discusses the technical and budgetary considerations of COMFIT rates, with the note that rate proposals will be addressed in separate testimony by ANSS.
Q. Who is the Alliance of Nova Scotia Sawmillers (ANSS)? A. The ANSS is a group of companies that own forest products manufacturing facilities located in Nova Scotia that have unified to ensure that the COMFIT CHP rate set by the NSUARB is...
AI summary The Alliance of Nova Scotia Sawmillers (ANSS) is a group of forest products manufacturing companies in Nova Scotia that have joined together to ensure the COMFIT CHP rate set by the NSUARB accurately reflects the rate needed for successful project development in the province.
Q. Has Synapse included an assessment of the power required to operate the CHP plant? - A. I do not see where Synapse has accounted for parasitic power losses associated with operating the power plant in their model. This is a significant...
AI summary Synapse has not accounted for parasitic power losses in the CHP plant model, which consume 14% of gross electricity production. Two options are presented: purchasing power at NSPI rates or self-consumption. Option 1 is deemed less costly for rate payers, but parasitic power losses must be included in the COMFIT rate calculation.
Introduction The Alliance of Nova Scotia Sawmillers (ANSS) is a group of forest industry companies that have unified to pursue the common goal of ensuring that there is a COMFIT available for biomass CHP and that the rate set for the COMFI...
AI summary The Alliance of Nova Scotia Sawmillers (ANSS) supports the NSUARB and Synapse's transparent process for determining COMFIT rates for biomass CHP. ANSS seeks to contribute to ensuring fair rates that reflect accurate generation costs and provide a fair return to project proponents.
4. IRs from the Alliance of Nova Scotia Sawmillers (ANSS) ANSS IR 1. Reference Draft COMFIT Tariffs: Initial Calculations and Discussions, p. 7, Table 1, (a) Why has Synapse assumed 100% corporate ownership of biomass CHP projects? Answer:...
AI summary The Alliance of Nova Scotia Sawmillers (ANSS) raises questions about Synapse's assumption of 100% corporate ownership of biomass CHP projects and the mechanisms available to account for fuel risk in ROE calculations for biomass CHP projects.
ANSS IR 7. Reference p. 4, Risk Factors (a) Does Synapse assume that proponents developing biomass CHP plants will have project management skills and resources beyond other technology developers for the COMFIT? What is the basis for that a...
AI summary Synapse initially assumed that biomass CHP plant developers would be corporations with strong project management skills, but is reevaluating this assumption after being advised that community-based groups may also develop such projects. Synapse acknowledges that Aboriginal groups, municipalities, universities, and other community groups may construct CHP plants in Nova Scotia.
07337Board Decision
6 passages
iscounted cash flow model. The intent of this approach is to determine a reasonable tariff which will facilitate a reasonable level of development activity for typical projects in that resource class. [54] The Board is mindful that differe...
AI summary The Board discusses the use of a 'typical cost' approach in determining COMFIT tariffs, aiming to balance reasonable rates for ratepayers with encouraging development activity. This approach considers different project characteristics but sets a single tariff per resource class.
[212] ANSS, in its reply submission stated: 30. Likewise, the risk of undue costs being borne by ratepayers is tempered by the reality that only a limited number of CHP Facilities will be likely to participate due to inherent limitations i...
AI summary ANSS argues that the risk of ratepayers bearing undue costs is limited due to the cap on biomass in the Act and Regulations, which restricts the number of CHP Facilities that can participate.
[217] When discussing the St. FX project, Synapse had problems with it being considered a CHP: ... And frankly, that's one of the concerns I would have about this project because it has an overall efficiency of 28 percent, and I would have...
AI summary The discussion centers on the St. FX project's classification as a CHP and its efficiency concerns, with Synapse criticizing its low efficiency and higher costs. St. FX recalculates the rate using the Synapse model but argues the model is not suitable for a university heating plant. The Board accepts Synapse's conservative COMFIT rate approach and plans a review in three years.
10.1 Submissions [235] Synapse proposed a tariff of $652 per megawatt hour for in-stream tidal projects. They based this tariff on a 500 kilowatt installation employing one or more instream tidal generators. Synapse assumed total project c...
AI summary Synapse proposed a $652 per megawatt hour tariff for in-stream tidal projects, based on estimated costs and a 37% capacity factor. The Consumer Advocate recommended a lower rate of $398 per megawatt hour, while Mr. Couture supported the higher rate but suggested tariff degression. The Province responded by indicating that tariff degression could be considered in future reviews.
[254] Brian Giroux also addressed this matter with the Synapse panel: '" did you guys do any analysis of the space within our distribution system to see if, in fact, there was room for some of these classes or some of these projects at all...
AI summary Brian Giroux raised concerns about the lack of analysis regarding distribution system capacity for COMFIT projects, suggesting that setting rates without considering available space may be ineffective. The EAC recommended a transparent grid information resource to support COMFIT and investor confidence, while NSPI argued that direct communication with developers was sufficient. The Board agreed that publicly available capacity information would assist developers and directed NSPI and municipal utilities to create such a resource.
[262] In its Closing Submission, the CA stated: The Consumer Advocate further recommends that the tariffs include the following express provisions that are to be met by the project. - Approval from the Energy Minister. - The requirements o...
AI summary The Consumer Advocate recommends that tariffs for renewable energy projects include provisions requiring approval from the Energy Minister, compliance with specific regulations, and adherence to capacity limits. The Board also imposed a limit on tidal power under the COMFIT rate to manage rate impacts similarly to small wind limitations.
07337Board Decision
9 passages
eferred to as "Biomass CHP" or "CHP". - [18] The Regulations also contain the following provisions relating to the generation capacity of various facilities: - 3(1) In the Act and these regulations, "developmental tidal array" means a gene...
AI summary The document outlines provisions in the Renewable Electricity Regulations, including definitions for tidal generation facilities and restrictions on biomass and wind power capacity. It specifies limits on primary forest biomass usage and feed-in tariff approvals for small wind power facilities.
5.5 Consideration of tariffs in other jurisdictions - [61] In assessing whether the proposed COMFIT tariffs are reasonable, Synapse, in addition to considering stakeholder feedback, compared the proposed tariffs "...to FIT prices adopted i...
AI summary The document discusses the evaluation of the proposed COMFIT tariffs in Nova Scotia by comparing them to FIT rates in other jurisdictions like Vermont and Ontario. Key differences include tax credits in the U.S., ownership requirements in Vermont, and project size eligibility. The Province supports Synapse's benchmarking approach, emphasizing the importance of considering these differences when assessing tariff reasonableness.
6.2.1 Submissions [71] In developing proposed tariff rates under the COMFIT models, Synapse did not make any specific assumptions about the project ownership. As noted earlier in this Decision, the approach that was adopted was to determin...
AI summary Synapse developed COMFIT tariff rates using a 'typical cost' approach, assuming no specific project ownership. The Board approved this method, but Synapse also considered the impact of different ownership structures on cost of capital and income tax treatment. Taxable and non-taxable project statuses significantly affect COMFIT rates, with larger impacts observed for tidal projects.
9.1.1 Findings on Definition [151] The Board finds that for a CHP facility to be entitled to a COMFIT it must produce both heat and steam, and that the primary purpose of the plant is to supply a steam host. [152] The Board also finds that...
AI summary The Board determines that a Combined Heat and Power (CHP) facility must produce both heat and steam with the primary purpose of supplying steam to a host, and that tariff costing for a typical CHP plant should be based on producing approximately 2MW of electricity.
[212] ANSS, in its reply submission stated: 30. Likewise, the risk of undue costs being borne by ratepayers is tempered by the reality that only a limited number of CHP Facilities will be likely to participate due to inherent limitations i...
AI summary ANSS argues that the risk of ratepayers bearing undue costs is limited due to the expected low participation of CHP facilities, constrained by system limitations and a biomass cap in the Act and Regulations.
10.1 Submissions [235] Synapse proposed a tariff of $652 per megawatt hour for in-stream tidal projects. They based this tariff on a 500 kilowatt installation employing one or more instream tidal generators. Synapse assumed total project c...
AI summary Synapse proposed a $652/MWh tariff for in-stream tidal projects, citing high costs and technology immaturity. The Consumer Advocate suggested a lower rate of $398/MWh. Mr. Couture supported the higher rate but raised concerns about uncertainties in tidal power. The Province suggested tariff degression and deferred detailed consideration to future reviews.
12.1 Distribution system capacity [253] During the proceedings, the parties made several references to limited capacity being available on certain distribution feeders, which could restrict the number or size of generators that could be co...
AI summary During the proceedings, parties highlighted concerns about limited distribution feeder capacity affecting generator connections. The EAC questioned Synapse on the importance of transparency in grid capacity information for COMFIT project development, with Synapse affirming that public availability would improve efficiency by removing barriers related to grid congestion visibility.
[254] Brian Giroux also addressed this matter with the Synapse panel: '" did you guys do any analysis of the space within our distribution system to see if, in fact, there was room for some of these classes or some of these projects at all...
AI summary Brian Giroux raised concerns about the lack of analysis on distribution system capacity for COMFIT projects. The EAC recommended a transparent grid information resource, while NSPI argued that current processes already provide sufficient information. The Board agreed that public capacity information would help developers and directed NSPI and municipal utilities to create and maintain such a resource by September 30, 2011.
[286] The Board adopted the following tariffs recommended by Synapse for the five classes of renewable low-impact electricity noted below, with the changes as directed by the Board in this Decision: - Wind power projects greater than 50 kW...
AI summary The Board approved Synapse's recommended tariffs for various renewable energy projects, with specific adjustments. The tariffs are set for 20 years, and a review of COMFIT tariffs is scheduled in three years. NSPI and municipal electric utilities are directed to provide publicly available information on generation interconnection capacity and file annual reports on COMFIT program participants.
20110405-1Hearing Transcript — 4/5/2011 (Synapse Panel, ANSS Panel)
6 passages
- DICTUM DIGITAL INC. CERTIFIED COURT REPORTERS You know, I'm a fisherman. You want 1 NSUARB-BRD-E-R.10 Page 301 to find good bait, you want to cast it out there and get 6 I'm assuming that the people who did the analysis of the 7 availabl...
AI summary The text includes a portion of a regulatory proceeding with participants discussing the analysis of available capacity and the implications of setting rates if there is insufficient capacity. There is also a mention of cross-examination and the involvement of Synapse Energy Economics.
- have any disagreement with. Page 372 NSUARB-BRD-E-R.10 1 In general, would you be able to 2 comment on whether they're gross capacity factors or net 3 capacity factors? 4 MR. RICKERSON: In the model, in the 5 margins it says "net of plan...
AI summary The discussion revolves around the distinction between gross and net capacity factors in a model, with the model using net capacity factors after accounting for plant availability and other loss factors. The model's approach was based on stakeholder consensus, and the net capacity factors range from 26% to 32% according to different reports.
- That difference, there's a - transformation in voltage between those two differences - which can also add to the electrical losses. - In addition, that distance, if you're - assuming 60 metres, well, then there's likely not going to - be...
AI summary The discussion focuses on the impact of distance on electrical losses in power lines, with a specific example of how losses increase with longer distances. The Chair references the Hatch Report and asks about capacity factors, but the witnesses are unable to provide a definitive answer.
- representative of appropriate gross capacity factors NSUARB-BRD-E-R.10 - rather than net, and that the uncertainty regarding the
AI summary The text discusses the consideration of appropriate gross capacity factors rather than net, highlighting uncertainty in the process. It references a specific board document (NSUARB-BRD-E-R.10) and touches on regulatory considerations related to capacity factors.
- interconnection specifically of which side of the - transformer the meter will be on is a significant unknown. - I mean, it's up to 5 percent. That's 5 percent of - revenue. It's a direct effect on revenue. - THE CHAIR: I guess what I'm...
AI summary The discussion focuses on the uncertainty regarding the location of a meter on a transformer and its impact on revenue, as well as the importance of accounting for losses in capacity factor models used by Nova Scotia Power.
- DICTUM DIGITAL INC. CERTIFIED COURT REPORTERS version of this exhibit, as an undertaking, we'd like to Page 406 NSUARB-BRD-E-R.10 1 instead of holding up the whole group. 2 Okay. MR. KEITH: 3 MR. DOEHLER: So if I understand, the 4 number...
AI summary The discussion revolves around the capacity factor (COMFIT) and the ability of different community groups, including municipalities and First Nations, to participate in the program. The witness explains that a representative midpoint was used to model participation, rather than considering each group's individual constraints. The conversation also includes an introduction from a representative of a wind energy company involved in projects in Nova Scotia.
20110407-1Hearing Transcript — 4/7/2011 (Consumer Adv. Panel, Cdn. Wind Energy Panel, EAC - T. Couture)
4 passages
Nova Scotia Power. Page 930 NSUARB-BRD-E-R.10 1 Most of the projects which are to come 2 have either recently or are to come online with Nova 3 Scotia Power are in areas of the province which are noted 4 for their high capacity factor. 5 I...
AI summary The discussion centers on the capacity factors of wind energy projects in Nova Scotia, with concerns raised about whether projects in high-capacity areas may distort evidence and affect the relevance of proposed adjustments. The Hatch Report is referenced, noting that no regions have lower capacity factors than estimated by Synapse. A trade-off between resource distribution and efficiency is highlighted, and the use of COMFIT for certain projects is mentioned.
- DICTUM DIGITAL INC. CERTIFIED COURT REPORTERS difference, but there may be some, depending upon how you 2 MR. PYNN: Okay, that's all I have. 14 reasonable thing from a market perspective? 15 MR. CHERNICK: Well, again, not 16 necessarily...
AI summary The discussion revolves around the feasibility of financing community projects using municipal, university, and community funds, and the capacity factors of various locations as outlined in the Hatch Report.
- percent. NSUARB-BRD-E-R.10 Page 1029 2 question, that you think that there's evidence that a 37 3 percent capacity factor exists to make you think that 4 that's the one that the Board should be using in a 5 reasonable fashion. Is that co...
AI summary The discussion revolves around the use of a 37 percent capacity factor for renewable energy projects, with the question of whether this is based on actual production data or theoretical projections from unfunded projects. The witness clarifies that the data comes from filings by project proponents and is used by NSPI for compliance with its renewable electricity standard.
- DICTUM DIGITAL INC. CERTIFIED COURT REPORTERS inputs, is it appropriate to consider the cost of putting 1 a plant on the ground in practice or in theory? 2 MR. COUTURE: It's necessary to 3 consider the costs that a real project would inc...
AI summary The discussion centers on the challenges of obtaining debt financing for biomass CHP projects, citing factors such as project size, inexperience, fuel volatility, grid connection delays, and reliability concerns. The witness acknowledges these challenges but suggests that while debt may be available, it would likely come with more stringent terms.