N-1Report
9 passages
.................................................................................................... 20 15 3.2.5 Rate Base Procurement ...........................................................................................................
AI summary The document outlines sections covering rate base procurement, unit utilization forecasts, system impact studies, environmental regulatory requirements, and resource adequacy. Key themes include energy mix evolution, transmission service queues, renewable electricity mandates, and environmental policy updates.
Victoria Junction Light Fuel Oil 66 Total Combustion Turbine 231 Pre-2001 Renewables Independent Power Producers (IPPs) 25.7 Post-2001Renewables (firm) IPPs 64.3 NS Power wind (firm) Wind 14.5 Community-Feed-in-Tariff (firm) 8 7F IPPs 29.6...
AI summary The document corrects the Mersey system's firm capacity alignment with an ELCC adjustment, notes Annapolis out of service, Lingan Unit 2 in cold reserve until 2027, and specifies 18% firm capacity from ERIS/NRIS wind projects, referencing sections 3.1.2, 3.2.3, 3.2.4, and 6.3.
3 The NS Power 2024 ACE Plan and Path to 2030 included sustaining capital investments in the 4 Mersey Hydro System (MHS) which will ensure safe and reliable water management throughout 5 the timeframe required to complete adequate prelimin...
AI summary NS Power's 2024 ACE Plan and Path to 2030 emphasizes sustaining investments in the Mersey Hydro System (MHS) regardless of redevelopment or decommissioning, citing economic benefits and contributions to renewable energy targets. The MHS provides 45.8 MW capacity and 220 GWh annually toward NS Power's goals, with updated reliability metrics reflecting its role in system planning.
nitor the development of these potential resources and reassess as needed. Figure 22 5 below shows the anticipated DSM and firm capacity changes over the ten-year period 23 starting in 2025. 24 DATE FILED: June 27, 2024 Page 15 of 67 2024...
AI summary The text discusses the monitoring of potential resources and reassessment as needed, referencing Figure 22.5, which shows anticipated DSM and firm capacity changes over a ten-year period starting in 2025.
MW • Firm capacity: 12 MW20 2033/2034 Wind – Future Procurements • Installed capacity: 200 MW • Firm capacity: 12 MW20 1 2 3.2.2 Brooklyn Power 3 4 Brooklyn Power owns a 24 MW firm dispatchable renewable energy biomass facility located in...
AI summary The document outlines the current status of various energy generation facilities, including Brooklyn Power's 24 MW biomass facility and Lingan Unit 2, which was placed in cold reserve in August 2022. Lingan Unit 2 was recalled multiple times during the 2023/2024 winter to support firm customer load. NS Power is maintaining existing thermal units in cold reserve to ensure planning reserve margin as new firm capacity resources are added to the system.
Non-Confidential 1 6B(2)(b) of the Renewable Electricity Regulations 22 as part of meeting NS Power’s 2030 21F 2 Decarbonation Goals. 3 4 The RBP portfolio was announced on August 17, 2022 and subsequently updated on July 12, 2023 5 and Fe...
AI summary The RBP portfolio, part of NS Power's efforts to meet decarbonization goals, was initially announced in 2022 and has since been updated. One project withdrew, reducing the total capacity and energy from five to four projects. The withdrawn project's capacity will be added to the Green Choice procurement round, increasing its maximum capacity. The report also discusses unit utilization forecasts and the evolution of Nova Scotia's energy mix.
Unit 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 TRE-5 L L L L - - - - - - - TRE-6 H H H H M L - - - - - TUC-1 M M L L L L UL UL UL UL UL TUC-2 H M M M M H H H M M H TUC-3 H H M H M H H H H H H TUC-4 H H H H H H H H H H H TUC-5...
AI summary The text discusses projected sustaining investments for various units, based on utilization forecasts and failure mechanisms. It highlights that NS Power does not account for unplanned failures in these estimates and explains how different asset classes are evaluated, with some prorated by utilization factor and others influenced by additional factors.
1 6.3 Capacity Contribution of Renewable Resources in Nova Scotia 2 3 Due to their variability, renewable energy resources such as wind and solar are not always available 4 to contribute during peak demand hours. The Effective Load Carryin...
AI summary The document discusses the capacity contribution of renewable resources in Nova Scotia, focusing on the Effective Load Carrying Capability (ELCC) of wind and solar energy. The NSUARB directed NS Power to conduct a Capacity Study to calculate ELCC values for existing and potential new wind resources, with results showing a declining marginal ELCC as more wind is added to the system.
1 NS Power supports updating the capacity study prior to the next IRP analysis, with the focus of 2 the update being an examination of the interactive effect of the identified clean resources (wind, 3 solar, battery energy storage, and dem...
AI summary NS Power supports updating the capacity study prior to the next Integrated Resource Plan (IRP) analysis, focusing on the interactive effects of clean resources. Municipal load in certain areas is served by a wind farm not included in NS Power’s sourced wind generation. Due to increased firm peak demand and delays in the Wreck Cove LEM Project, NS Power will not meet the 20% PRM target for the 2024/2025 Winter period and will implement strategies like keeping Lingan 2 in cold reserve.
N-3NSPI (NSUARB) RIR-1 - RIR-18
3 passages
ed clean resources (wind, solar, battery 31 energy storage, and demand response). As a starting point for this work, NS Power will 32 develop a draft scope of work and project schedule to be circulated to IRP stakeholders for 33 comment by...
AI summary NS Power is developing 300 MW of new firm capacity for Winter 2027/2028, with studies on technology, supply chain, and grid integration progressing. A second 300 MW for 2029/2030 will follow a similar model. Environmental studies and permitting will continue into 2025. The Hybrid Peak mitigation program is referenced in another document.
1 Request IR-3: 2 3 Figure 3 shows the Nova Scotia Block with a maximum rated capacity of 145.4 MW 4 during the winter peak period. In its response to Board IR-3 in Matter M11221, NS 5 Power stated that the NS Block includes the provision...
AI summary The document discusses NS Power's use of a 95% ELCC (Effective Load-Carrying Capacity) assumption for the Nova Scotia Block in its 10-Year System Outlook Report, contrasting with a 98% ELCC in prior studies. It requests updated data, continuation of the assumption, and examples of peak demand periods exceeding 145.4 MW. NS Power references recent reports from NSPML and ENL on system reliability but does not confirm new data acquisition.
units or transmission assets, etc. The amount of available reserve capacity for the Winter 29 2024/2025 means NS Power has sufficient capacity to serve firm customers uninterrupted Date Filed: September 19, 2024 NSPI (NSUARB) IR-17 Page 1...
AI summary NS Power has sufficient reserve capacity to serve firm customers uninterrupted during the Winter 2024/2025, as outlined in the 2024 10-Year System Outlook Report. The report was filed on September 19, 2024, as part of NSPI's responses to NSUARB Information Requests.