N-2NSPI (NSEB) RIR 1 to 4 - Redacted
2 passages
1 3 By 2026, the unit has accumulated approximately 340,000 hours with 650 start/stop cycles. CI C0080671 – LIN1 HP IP Turbine Refurbishment 2026 (NSEB M12745) NSPI Responses to NSEB Information Requests
AI summary The document references a turbine refurbishment project for NSPI by 2026, with the unit having accumulated 340,000 hours and 650 start/stop cycles.
CONFIDENTIAL (Attachment Only) 1 Request IR-3: 2 3 (a) Was an engineering assessment performed that recommended the proposed overhaul 4 of the components? If yes, please provide the report. If not, please explain why no 5 assessment was co...
AI summary The response to Request IR-3 indicates that no engineering assessment was performed for the proposed overhaul of turbine components, as the decision was based on maintenance strategy targets. Contract estimates were derived from previous project quotes and reviewed by subject matter experts. Risks covered by the 20% contingency are not explicitly detailed.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →