Matter: Nova Scotia Power Inc. - CI C0069166 - POT Turbine Valve Refurbishment - $1,544,021 2025 ACE Plan Capital Items for Subsequent Approval: CI C0069166 - POT Turbine Valve Refurbishment - $1,544,021 2025 ACE amount $2,872,598 $1,544,021 spent as at March 31, 2026 Partially Confidential
1 passage 1 document

Capacity Market Participation across all matters →

N-1CI C0069166 - POT Turbine Valve Refurbishment - Report - Redacted 1 passage
Why do this project now? p. p. 11
Why do this project now? The Unit 2 Main Steam Valves were last inspected in 2021, and the Reheat Intercept Valves were last inspected in 2019. The accumulated operating hours since those last inspections resulted in both components reachi...

AI summary The project to inspect and maintain Unit 2 Main Steam Valves and Reheat Intercept Valves was critical to prevent potential outages, safety hazards, and regulatory noncompliance. The valves were last inspected in 2021 and 2019, respectively, and reached maintenance thresholds. The project was completed in October 2025 and finalized in December 2026 due to the need for financial reconciliation following a cyber event.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →