Matter: CI# 39471 - P-510 - NSPI WO - TRE6 - U&U PA Damper Replacement - $603,418Zero dollars spent to date
12 passages 4 documents

Capital Expenditures across all matters →

N-1Non-Confidential Work Order 6/29/2010 6 passages
p. p. 1
POWER An Emera Company UARB APPROVAL SHEET TRE6 - (U&U) PA Damper Replacement Project Title: CI Number: 39471 II Capital Project Authorization Head Office Use: D ATO Project Number: D Final Cost Date: April 30, 2010 Location: Division: Exp...

AI summary This document is an approval sheet for a capital project authorization related to the replacement of a damper at a power facility. The project, submitted by Nova Scotia Power Incorporated, has an estimated cost of $603,418 and is scheduled to start in April 2010, with an estimated in-service date of May 2010. The approval is granted by the Nova Scotia Utility and Review Board.

Section 3 p. p. 1
39471 • TRE6 - PA Damper Replacements Project Number Parent CI Number Cost Centre 345 - 345-Trenton unit 6 Capital

AI summary The text references a project titled 'TRE6 - PA Damper Replacements' under Parent CI Number 345-Trenton unit 6 Capital, indicating a capital investment related to damper replacements.

8udget Version - 201003/09 Forecast p. p. 1
8udget Version - 201003/09 Forecast Forecast Start 04/01/2010 Operational 05/15/2010 Final Cost 05/30/20't 0 2010 $603,418.111 Total: $603,418.11 Origina[Cost. : $430,000.00 The scope of work for this project includes replacement of the 6A...

AI summary The document outlines a budget version for a project with a forecast start date of April 1, 2010, and a final cost of $603,418.11. The project involves replacing various dampers in the primary air duct work to coal pulverizers at locations 6A and 68.

Section 5 p. p. 1
Summary of Related CI's +/- 2 years No projects in 2008,2009,2010,2011 and 2012 Cl Number : 39471 - TRE6 - PA Damper Replacements Project Number Parent Cl Number : - Approved Date Cost Centre : 345 - 345-Trenton unit 6 Capital Budget Versi...

AI summary The text provides a summary of capital investment (CI) projects, noting no projects between 2008 and 2012, and details a specific project, TRE6 - PA Damper Replacements, with a parent Cl Number 39471 and Cost Centre 345-Trenton unit 6 Capital.

2010 03/09 Forecast p. p. 1
2010 03/09 Forecast Acct Actv Account Activity Forecast Amount Amount Variance 094 094 - Interest Capitalized 3,976 0 3,976 095 095-Thermal Overtime Labour AO 662 0 662 095 095-Thermal & Hydro Contracts AO 23,805 0 23,805 095 095-Thermal R...

AI summary The document presents a forecast for the 2010 03/09 period, detailing various accounts and activities with forecast amounts and variances. It includes entries related to interest capitalized, labor costs, materials, and contracts, as well as a total cost and original cost. The CI Number 39471 TRE6 - (U&U) PA Damper Replacements is also mentioned.

Capital Item Justification p. p. 1
Capital Item Justification Justification Criteria: Thermal Sub-Criteria: Maintenance Name of Report : Document Location : Person Responsible :

AI summary The document outlines a capital item justification framework under the 'Thermal' criterion with a sub-criteria focus on 'Maintenance.' However, no specific arguments, entities, or detailed analysis are provided in the text beyond structural headings and empty fields.

79547Board Decision Letter 1 passage
By Email and Courier p. p. 0
By Email and Courier Ms. Lee Thomson-Lutz, MBA, CMA Manager, Capital Nova Scotia Power Inc. 14 1 h Floor, Barrington Tower P. 0 . Box 910, Scotia Square Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of U&U Work Ord...

AI summary The Board approved NSPI's request for $603,418 to replace dampers at Trenton Unit 6, citing necessity for safe operation and risk of future outages if delayed. The project was deemed prudent to complete during the 2010 planned shutdown.

79547Board Decision Letter 1 passage
By Email and Courier p. p. 0
By Email and Courier Ms. Lee Thomson-Lutz, MBA, CMA Manager, Capital Nova Scotia Power Inc. 14 1 h Floor, Barrington Tower P. 0 . Box 910, Scotia Square Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of U&U Work Ord...

AI summary The Board approved NSPI's request for $603,418 to replace dampers at Trenton Unit 6, citing safety, reliability, and the risk of future outages if delayed. The project was deemed prudent to complete during the 2010 planned shutdown.

79548Approval Sheet [Signed by Board] 4 passages
Cost Centre 345 - 345-Trenton unit 6 Capital Budget Version - 2010 03/09 Forecast p. p. 1
Cost Centre 345 - 345-Trenton unit 6 Capital Budget Version - 2010 03/09 Forecast Forecast Start 04/01/2010 Operational 05/1512010 Final Cost 05130/2010 2010 $603,418.11 Total : $603,418.11 Original Cost : $430,000.00 The scope of work for...

AI summary This document provides a forecast for the capital budget of Cost Centre 345-Trenton unit 6 in 2010, outlining the scope of work for replacing various dampers and duct work related to coal pulverizers.

Section 93 p. p. 1
Summary of Related Cl's +/. 2 years No projects In 2008,2009,2010,2011 and 2012 Cl Number 39471 TRE6 - PA Damper Replacements Project Number Parent Cl Number Approved Date ~ Cost Centre 345 345-Trenton unit 6 Capital Budget Version 2010 03...

AI summary The text summarizes a project related to damper replacements at the Trenton unit 6, with details on the cost centre, budget version, and forecast date. The project was not implemented in the years 2008 to 2012.

Capital Item Accounts p. p. 1
Capital Item Accounts Acct Act>J Account Activity Forecast Amount Amount Variance 094 094 - Interest Capitalized 3,976 0 3,976 095 095-Thennal Overtime Labour AO 662 0 662 095 095-Thermal & Hydro Contracts AO 23,805 0 23,805 095 095-Therma...

AI summary The document presents a table of capital item accounts with forecast amounts, actual amounts, and variances. The table includes accounts related to interest capitalized, labor costs, contracts, and materials for thermal and hydro operations, as well as power production. The total forecast cost is $603,418, with an original cost of $430,000.

Capital Item Justification p. p. 1
Capital Item Justification Justification Criteria : Thermal Sub-Criteria : Maintenance Name of Report : Document Location : Person Responsible :

AI summary A section outline for capital item justification under thermal maintenance criteria, with placeholders for report details and responsible personnel. No substantive content or arguments are present in the provided text.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →