NSPI Capital Item CI# 29009 Right of Way Purchase Northern NS p. p. 20
NSPI Capital Item CI# 29009 Right of Way Purchase Northern NS In jurisdictions across North America it is becoming more difficult to obtain access to the land and the rights of way necessary to undertake transmission projects. It is estima...

AI summary NSPI plans a second 345kV transmission line to New Brunswick, citing challenges in securing right-of-way access and estimating a $200M cost with a 5-year timeline. The project, part of the 2010 ACE Plan, requires regulatory approval by June 2010 to address evolving electricity market needs.

8.0 TRANSMISSION DEVELOPMENT 2010 TO 2018 p. p. 20
8.0 TRANSMISSION DEVELOPMENT 2010 TO 2018 Transmission development plans are summarized below. As discussed earlier, these projects are subject to change. For 2010, the majority of the projects listed are included in the 2010 Annual Capita...

AI summary The document summarizes transmission development plans from 2010 to 2018, noting that 2010 projects were included in the Annual Capital Expenditure (ACE) Plan, while subsequent projects are listed by projected completion year. Plans are subject to change.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →