N-1Non-Confidential Work Order 7/30/2010
9 passages
An Emera Company UARB APPRO VAL SHEET Project Title: TRE-Unit #6 Low Nox Combustion F iring System Ci Number: 28866 Capital Project Authorization Head Office Use: Пато Project Number: S265 Final Cost Date: July 30, 2010 . — Location: Divis...
AI summary This document outlines a capital project related to the TRE-Unit #6 Low Nox Combustion Firing System, including budget estimates, project estimates, and spending details. The project was authorized by the Nova Scotia Utility and Review Board, with a variance between approved and actual spending.
-Post outage performance testing of the Low NOx Combustion Firing System. Capital Item Accounts Acct Actv Account Activity Forecast Amount Amount Variance 001 Regular Labour (No AO) 001 - 31,887 0 31,887 001 THERMAL Regular Labour 001 - 72...
AI summary The text provides a detailed breakdown of capital item accounts related to the post-outage performance testing of the Low NOx Combustion Firing System. It includes various labor, materials, and consulting costs, with a total cost of $4,106,621.
Parent CI Number Approved Date 11/8/2007 Cost Centre 345 345-Trenton unit 6 Capital Budget Version 2010 06/06 Forecast CI Number 28866-S265 Parent CI Number Cost Centre 345 345-Trenton unit 6 Capital TRE-UNIT#6 LOW NOX COMBUSTION FIRIN Pro...
AI summary The document outlines a capital budget entry for the TRE-UNIT#6 LOW NOX COMBUSTION FIRIN project under Cost Centre 345-Trenton unit 6, approved on 11/8/2007. The justification criteria include environmental considerations, though specific details are not provided.
Project Number Unit #6 Trenton- Low Nox Combustion Firing System CI #28866-5265 Account Activated Actual Variance Explain Variance Less regular plant trades and engineering resouces required. Some of the work was Labour 001 - $310,000 $143...
AI summary The document details the financial variances for Unit #6 in Trenton, including lower-than-expected labour and contract costs, increased overtime and travel expenses, and savings from consulting work. The differences are attributed to changes in procurement processes, unexpected work during maintenance outages, and the use of internal resources.
Capital Management System Capital Item Detail Forecast Page: 1 of 4 Date: 2007/09/21 CI Number: 28866 - TRE-UNIT#6 LOW NOX COMBUSTION FIRING SYTEM Parent CI Number: Responsibility: 05270000 - GENERATION SERVICES Cost Centre: 345 - Trenton...
AI summary This document details a capital project to install a low NOx combustion firing system at Trenton Unit 6. The project includes installation, testing, and training, with a total forecasted cost of $5,607,640. The project is part of a special initiative under the Capital Management System.
Capital Item Accounts Forecast Acct Actv Div Account Activity Amount Amount Variance 094 005 0527 INTEREST CAPITALIZED 005 Indirect Costs 132,630 a a 095 005 0527 CONSTRUCTION OVERHEAD 005 Indirect Costs 170,510 a a 001 013 0527 REGULAR LA...
AI summary The document presents a table of capital item accounts with forecasted amounts and variances, detailing various expenses such as interest capitalized, construction overhead, labour costs, contracts, and other goods and services related to the Boiler and Design activities.
Work Order Requests Pending UARB approval, in 2008 NSPI will undertake the third year of its four year NOx Reduction program. Three low NOx retrofits are required for Lingan Unit 1 eel 28867), Point Tupper Unit 2 eel 28865), and Trenton Un...
AI summary NSPI seeks UARB approval for the third year of its four-year NOx Reduction program, involving three low NOx retrofits at Lingan Unit 1, Point Tupper Unit 2, and Trenton Unit 6, with estimated costs of $4.1 million. Higher costs for Trenton 6 are attributed to boiler design complexity and market price fluctuations. The work scope includes equipment installation, testing, and staff training.
The following table provides a summary of the schedule of work included in the three capital projects. Task Lingan Unit 1 Pt Tupper Unit 2 Trenton Unit 6 Submission to DARB September 2007 Authorize vendor to proceed November 2007 Delivery...
AI summary The table outlines the schedule of work for three capital projects, including key milestones such as submission to DARB, authorization to proceed, delivery to site, start of outage, completion of work, and guarantee testing for Lingan Unit 1, Pt Tupper Unit 2, and Trenton Unit 6.
Capital Project Estimate Sheet Name of Project: Lingan Unit 1 - Low NOx Combustion Firing System- JULY 20,2007 ESTIMATE Project No • Division Power Production Generation Services Estimated Completion Date: 2008 . Capital Item No. Responsib...
AI summary This document is a capital project estimate sheet for the installation of a Low NOx Combustion Firing System at Lingan Unit 3. It includes cost estimates for design, supply, and commissioning, with details on labor, travel, and consulting expenses.