N-1Redacted Work Order 9/2/2010 6 passages
Section 27 p. p. 1
Parent CI Number Cost Centre 340 - 340-Trenton Unit 5 Capital Budget Version - 201007/05 Forecast Forecast Start 08/01/2010 Operational 09/30/2010 Final Cost 11/30/2010 2010 $637,704.60 Total: $637,704.60 Original Cost: $350,000.00 The pur...

AI summary The project aimed to repair the damaged governor on Trenton Unit 5 following an unplanned outage in March 2010. The repair was necessary due to failure caused by insufficient backlash and tooth clearance between the worm and wheel, resulting from normal wear. The work was completed during the outage, with the total cost exceeding the original budget.

Summary of Related Cl's +1- 2 years. No other projects in 2008,2009,2010,2011 or 2012 p. p. 1
Summary of Related Cl's +1- 2 years. No other projects in 2008,2009,2010,2011 or 2012 201007/05 Forecast Variance 10,515 6,088 20,711 11,912 9,794 37,000 46,000 45,000 121,000 316,200 3,000 21,000 648,220 Approved Date Budget Version Amoun...

AI summary The document summarizes related capital projects from 2008 to 2012, with a focus on the 201007/05 forecast, including details on forecast amounts, variance, and specific capital items such as the 340-Trenton Unit 5 Capital project and the Turbine Governor Refurbishment Project.

Section 29 p. p. 1
CI Number 39663 TRE5 - (UU) Turbine Governor Refurb Project Number Approved Date Parent CI Number Cost Centre 340 340-Trenton Unit 5 Capital Capital Item Justification Justification Criteria: Thermal Sub-Criteria: Maintenance Name of Repor...

AI summary The Turbine Governor Refurb Project at Trenton Unit 5 is necessary to return the unit to service and avoid replacement energy costs. The project involves replacing the worm & wheel, rebuilding governors, and adjusting overspeed trip mechanisms to meet OEM standards, ensuring cost-effectiveness and timely completion.

TRENTON GENERATING STATION - PROJECT COST ESTIMATE (2010) p. pp. 1-6
TRENTON GENERATING STATION - PROJECT COST ESTIMATE (2010) FP# : 39663 Title : TRE5 - (UU) Turbine Governor Refurbishment Item Description Acct Actv Unit Quantity Unit Price Total 1 Supply of Materials 1.1 Wormwheel (March outage) Each 1 1....

AI summary The document provides a detailed breakdown of the project cost estimate for the Trenton Generating Station in 2010, focusing on the refurbishment of the turbine governor. It includes line items for materials, equipment rental, and plant labour costs associated with various outages.

Budget Year: Date: Division: CI Number: Department: Project No. : p. p. 6
Budget Year: Date: Division: CI Number: Department: Project No. : 23-A ug-1 0 8888287872 - 31 300088888 396 363 111113233 Alternative After Tax WACC PV of EVA / NPV Rank IRR Disc Pay Α Refurbish turbine governor 6.55% 3,163,190 1 67.34% 2....

AI summary The document presents a financial analysis of several projects, including the refurbishment of a turbine governor and multiple tests. It includes metrics such as after-tax WACC, PV of EVA/NPV, IRR, and discounted payback period. The refurbishment project ranks highest with a positive NPV and a high IRR.

Preamble p. pp. 6-8
,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3 2,540.3...

AI summary The text includes repeated numerical values and a mention of a turbine governor refurbishment project. The numerical data may relate to financial figures or costs, and the project is referred to as TRE5 (UU) Turbine Governor Refurbishment.

75527Board Decision Letter 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14 th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI Request for Approval of Unforeseen and Unbudgeted ("U&U") Work Order Less Than...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $648,220 Unforeseen and Unbudgeted (U&U) turbine governor refurbishment at Trenton Unit 5. The Board approved the expenditure, citing necessity to restore the unit and avoid replacement energy costs after a March 2010 failure.

75527Board Decision Letter 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14 th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI Request for Approval of Unforeseen and Unbudgeted ("U&U") Work Order Less Than...

AI summary The Board approved Nova Scotia Power Inc.'s request for $648,220 to refurbish a failed turbine governor at Trenton Unit 5, necessary to restore service and avoid replacement energy costs. The expenditure was deemed justified based on submitted information.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →