N-1Work Order
4 passages
Parent CI Number Cost Centre 345 - 345-Trenton unit 6 Capital Budget Version - 201007/05 Forecast Forecast Start 08101/2010 Operational 09/30/2010 Final Cost 10/31/2010 2010 $608,704.38 Total: $608,704.38 Original Cost: $430,000.00 The pur...
AI summary This document outlines a capital budget for the repair and replacement of components in the Trenton #6 boiler's superheater and reheat sections. The project was driven by inspection results and aimed to ensure reliable boiler performance. The work included tube replacements, design modifications, and shield repairs, and has been completed.
38854 - TRE6 - 6A Boiler Feed Pump Oil Cooler Upgrade $77,080 201007/05 Forecast Variance 7,970 34,976 31,773 419,713 114,272 608,704 Approved Date Budget Version Amount 0 0 0 0 0 0 Forecast Amount 7,970 34,976 31,773 419,713 114,272 608,7...
AI summary The text presents a capital item budget for a boiler feed pump oil cooler upgrade at TRE6, with forecast amounts and variances listed. It includes details on cost centers, account numbers, and capitalized interest. The document also references another capital item related to boiler superheater/reheater repairs.
Project Number CI Number 39602 TRE6 - (UU) Boiler Superheater/Rehe Project Number Approved Date Parent CI Number Cost Centre 345 345-Trenton unit 6 Capital Capital Item Justification Justification Criteria: Thermal Sub-Criteria: Maintenanc...
AI summary This document provides details for a capital project related to the Trenton unit 6 boiler superheater/reheater, including project number, cost centre, and justification criteria under thermal maintenance.
TRENTON GENERATING STATION - PRO )JE CT C OSTE S FIMATE (20 10) FP#: 39602 Title : TRE6 - (UU) Boiler Superheater/Reheater Repairs Item Description Acct Actv Unit Quantity Į Jnit Price Total 1 Supply of Materials 1.1 Tubing 012 013 Lot 1 $...
AI summary The document outlines the cost estimate for repairs at the Trenton Generating Station, including material supply, contractor labor, engineering, project management, indirect costs, and retirement costs. The total estimated cost is $608,704.38, with a significant portion allocated to contractor labor and retirement costs.
79546Approval Sheet [Signed by Board]
7 passages
VP Technical and Construction An Emera Company UARB APPRO VAL SHEET Project Title: TRE6 - U&U Boile r Superheater/Rehe eater Repairs CI Number: 39602 Capital Project Authorization Head Office Use: ☐ ATO Project Number: Final Cost Date: Nov...
AI summary This document outlines a capital project for boiler superheater/reheater repairs by Nova Scotia Power Inc., submitted to the Nova Scotia Utility and Review Board. The project, with an estimated cost of $608,704, was initiated in 2010 and completed by October 2010.
Cost Centre 345 - 345-Trenton unit 6 Capital Budget Version - 201 O 07/05 Forecast Forecast Start 08/01/2010 Operational 09/30/2010 Final Cost 10/31/2010 2010 $608,704.38 Total : $608,704.38 Original Cost : $430,000.00 The purpose of this...
AI summary The document outlines the capital budget for the replacement and repair of components in the Trenton #6 boiler's superheater and reheat sections. The project was driven by inspection results and aimed to ensure reliable performance. The work was completed with a total forecast cost of $608,704.38.
Budget Version 2010 07/05 Forecast Capital Item Accounts Acct Actv Account Activity Forecast Amount Amount Variance 094 094 - Interest Capitalized 7,970 0 7,970 095 095-Thermal & Hydro Contracts AO 34,976 0 34,976 012 013 012 - Materials 0...
AI summary The document presents a budget forecast for the year 2010, focusing on capital item accounts. It outlines various costs associated with different projects, including interest capitalized, thermal and hydro contracts, and power production contracts. The forecast amounts and variances are provided for each account.
Capital Item Justification Justification Criteria : Thermal Sub-Criteria : Maintenance Name of Report : Document Location : Person Responsible :
AI summary The 'Capital Item Justification' section outlines a framework for evaluating capital expenditures, focusing on thermal criteria and maintenance sub-criteria. However, the provided text contains no substantive content, as fields like 'Name of Report' and 'Person Responsible' remain unfilled, offering no specific arguments or factual details.
FP#: 39602 Title: TRE6 - (UU) Boiler Superheater/Reheater Repairs Item Description Acct Actv Unit Quantit~ Unit Price Total 1 Supply of Materials 1.1 Tubing 012 013 Lot 1 $ 3,618.00 $ 3,618.00 1.2 Thermowell 012 013 Lot 1 $ 530.00 $ 530.00...
AI summary The document outlines the costs associated with the repair of a boiler superheater/reheater, including materials, contractor labour, engineering, project management, indirect costs, and retirement costs. The total estimated project cost is approximately $608,704.38, with a significant portion allocated to contractor labour and retirement costs.
Budget Year : Date: Division·: Cl Number: Department : Project No. : 100 23-Aug-10 用 : : 39602 Lin i Alternative After Tax WACC PV of EVA / NPV Rank A Repairs during 2010 Outage 6.55% 843,444 1 В Test 2 6.55% 0 2 С Test 3 6.55% 0 2 D Test...
AI summary The document presents a table with financial metrics for various projects, including alternative options, after-tax WACC, PV of EVA/NPV, and rankings. It includes IRR and discount payback periods for different scenarios, with some entries containing errors or zero values.
TRE6 (UU) Boiler Superheater/Reheater Repairs Year Outage vs Replaceme Capital CCA UCC CFBT Applicable Taxes CFAT Discount Factor PV of CF CNPV 2010 82,252.0 (608,704.0) 24,348 2 584,355.8 (526,452.0) (20,169.4) (546,621.4) (546,621.4) (54...
AI summary The document presents a detailed financial analysis of the TRE6 (UU) Boiler Superheater/Reheater Repairs from 2010 to 2023, including capital expenditures, tax considerations, and net present value calculations over time.