Document: 305605 (P-194) Date Filed: Sept. 22, 2023 NSUARB (NS Power) Page 1 of 4 1 Request IR-1: 2 Referencing page 6 of 59 and Figure 6 on page 19 of 59, NS Power stated that the results of the 3 2022 IRP evergreen scenario CE1-E1-R2 wer...
AI summary The document outlines six requests for clarifications and updates related to Nova Scotia Power's Integrated Resource Plan (IRP), including project status updates, interruptible load changes, capacity contributions from the Maritime Link, energy mix shifts, capital investment tables, and system upgrade details for TSR 400. Requests focus on data accuracy, project timelines, and alignment with regulatory expectations.
ter M06966 (2015 10- 30 Year System Outlook Report) stated: 31 32 On page 55 of the SO Report, NSPI noted that it continues to proceed with the 33 acquisition of a right-of-way to accommodate a second 345 kV circuit between 34 Nova Scotia...
AI summary NSP reported 86% completion of a second 345 kV circuit right-of-way between Nova Scotia and New Brunswick by late 2015, referencing Board approval for Capital Item #29009 (Matter M03348). The progress was detailed in the 2015 Year System Outlook Report.