REDACTED (CONFIDENTIAL INFORMATION REMOVED) March 9, 2026 C. Henwood Tidewater substation and feeder 92H-331. To address the customer's immediate service conditions, NS Power implemented a quick corrective action by replacing the customer'...
AI summary NS Power addressed voltage issues at Tidewater substation and feeder 92H-331 through immediate conductor replacement and long-term upgrades requiring NSEB approval, including substation upgrades, transformer replacement, and new feeder construction. Contingency plans are in place to ensure reliability during delays.