N-1Application - CI C0080101 539N-210 Big Island Subsea Cable Replacement
4 passages
NSEB APPROVAL SHEET Project Title: 539N-201 Big Island Subsea Cable Replacement CI Number: C0080101 Date: April 9, 2026 Expenditure Profile Type of Filing Year Budget Amount Project Estimate Capital Project Authorization Unforeseen and Unb...
AI summary The NSEB Approval Sheet outlines the expenditure profile and authorization for the 539N-201 Big Island Subsea Cable Replacement project, including budget amounts, project estimates, and approval statuses for the years 2025 through 2027.
Summary of Related CIs +/- 2 years : Pursuant to Section 11.2 of the CEJC, related CIs for Distribution projects include "work completed on the same asset class (Padmount transformers, Breakers, etc.) or in the same location (feeder, Trans...
AI summary The document outlines related Capital Investments (CIs) for Distribution projects under Section 11.2 of the CEJC, specifying asset classes like Padmount transformers and Breakers. No projects are listed for 2024–2028. Depreciation classes include Distribution Plant – Underground Conductors and Devices, with an estimated asset life of 40 years.
Retirement Information: • Categorization of Retirement: Accounting Policy 6420 - Retirement and Disposal of Capital Assets • Percentage of Asset Pool: 0.11%
AI summary The document references Accounting Policy 6420, which categorizes the retirement and disposal of capital assets, and notes that 0.11% of the asset pool is involved in this process.
Title: 539N-201 Big Island Subsea Cable Replacement Description Unit Quantity Un it Estimate To tal Estimate Cost Support Reference Completed Simi Projects (FP#'s Vehicle Ov erhead/ Vehicle Labour AO Ь. 0 1 7 1 1 $ 46,340 Sub-Total $ 46,34...
AI summary The document outlines cost estimates for the Big Island Subsea Cable Replacement project, including labor, overhead, and capitalized interest costs, with a total estimated cost of $4,388,679 and an original cost of $843,222.
102449Decision Letter
2 passages
M12799 – Nova Scotia Power Inc. – CI C0080101 – 539N-201 Big Island Subsea Cable Replacement – $4,388,679 On April 9, 2026, Nova Scotia Power Inc. (NS Power) filed a request with the Nova Scotia Energy Board (Board) for approval of a 2026...
AI summary Nova Scotia Power Inc. (NS Power) requested approval for the replacement of the Big Island Subsea Cable, with an increased project cost of $4,388,679 due to additional engineering requirements. The existing cable, installed in 1977, has exceeded its service life and poses a risk of extended outages. The Nova Scotia Energy Board issued information requests, to which NS Power responded, explaining the project's necessity and details.
NSEB APPROVAL SHEET Project Title: 539N-201 Big Island Subsea Cable Replacement CI Number: C0080101 Date: April 9, 2026 Expenditure Profile Type of Filing Year Budget Amount Project Estimate Capital Project Authorization 2025 2026 2027 1,1...
AI summary The NSEB Approval Sheet outlines the expenditure profile for the 539N-201 Big Island Subsea Cable Replacement project, including budget amounts, project estimates, and types of filings for the years 2025 to 2027, with a total estimated cost of $4,388,679.
101647NSEB (NSPI) IR-1 to IR-16
5 passages
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPLICATION by NOVA SCOTIA POWER INCORPORATED (NS Power) for Subsequent Approval of an ACE Plan Capital Item CI C0080101 – 539N-210 Big Island...
AI summary The Nova Scotia Energy Board is considering an application by Nova Scotia Power Incorporated (NS Power) for subsequent approval of a capital item under the 2025 ACE Plan, specifically for the replacement of the Big Island Subsea Cable. The proceeding falls under the Public Utilities Act.
Request IR-3: - a. Please explain whether the proposed project budget includes any related onshore and near-shore land works and any associated equipment that may be required. - i. If not, please explain. - ii. If yes, please identify and...
AI summary Request IR-3 seeks clarification on project budget details, including onshore/near-shore land works and equipment, subsea cable installation methods, testing/commissioning plans, and warranty terms for new subsea cables.
Request IR-12: - a. For the listed consulting works in the Capital Project Detailed Estimate, please provide all relevant studies and technical reports prepared for the project, including cable engineering design and routing, metocean data...
AI summary Request IR-12 seeks technical reports, consultant scopes, and concerns related to a capital project's detailed estimate, including environmental and technical studies such as cable design, metocean data, and habitat assessments.
Request IR-15: - a. Has NS Power procured the services of a cable laying vessel for this project? - i. If not, what is the schedule for procuring such services? - A. If a vessel cannot be secured by this timeline, please identify any furth...
AI summary Request IR-15 asks whether NS Power has procured a cable laying vessel for a project, the timeline for procurement if not, and potential risks to project costs if procurement is delayed. The focus is on project execution risks and cost implications.
Request IR-16: - Please explain specifically how NS Power developed its cost estimates for each line item under - "Materials" and "Contracts" in the "Capital Project Detailed Estimate" on pdf pg. 5 of the - application.
AI summary Request IR-16 asks NS Power to detail its methodology for estimating costs under 'Materials' and 'Contracts' in the 'Capital Project Detailed Estimate' on page 5 of its application, seeking transparency in capital expenditure planning.