Matter: NSP Maritime Link Inc. (NSPML) - 2026 Q1 Quarterly Report
4 passages 2 documents

Capital Expenditures across all matters →

N-1Report - Redacted 3 passages
1 engineering and planning activities progressed in order to prepare for the upcoming p. pp. 8-10
Recommendation number 1 is closed. 1 engineering and planning activities progressed in order to prepare for the upcoming 13 During the 2026 Assessment hearing in December 2026, NSPML agreed to provide a 14 quarterly update on LTAMP progres...

AI summary The document discusses the progression of engineering and planning activities for the upcoming Maritime Link Project, including a quarterly update on LTAMP progress and an updated cost summary reflecting the Board's decision on unrecoverable costs and adjusted AFUDC figures.

e) Capital (Land assets) p. p. 19
e) Capital (Land assets) • Minor sustaining capital expenditures are planned for 2026 for recurring smaller expenditures including any maintenance, repairs, alterations, improvements, replacements, renewals and additions to continue optimi...

AI summary The document outlines planned minor sustaining capital expenditures for 2026, focusing on maintenance, repairs, and improvements to optimize the ML HVDC facilities. These expenditures aim to ensure ongoing operational efficiency and infrastructure sustainability.

f) Capital (Marine assets) p. p. 19
f) Capital (Marine assets) • Part 2 of subsea rock installation to improve nearshore cable protection.

AI summary The document outlines Part 2 of a subsea rock installation project aimed at enhancing nearshore cable protection as part of marine asset capital expenditures.

102327Board letter re: Accepted as file with duther updates to be included in the next report 1 passage
M12808 - NSP Maritime Link Inc. - Q1 2026 Quarterly Report p. p. 0
it is available. - ii. On page 3 of the report, it states: "Pole 1 reactor door expansion during high outside temperatures initiated a pole trip (July 2025). Solution is pending." Please provide the details of this pole trip, and the timel...

AI summary The document outlines several inquiries and updates related to the NSP Maritime Link Inc. (NSPML) Q1 2026 quarterly report. Key topics include pole trip details, a mass outage due to communication issues, progress on the Labrador Island Link test results, the Long-Term Asset Management Plan (LTAMP) update, and capital cost breakdowns. The Board also emphasizes the importance of the Regulation Service Agreement and potential disallowances if not completed on time.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →