Topic/Matter Intersection

Topic:"Capital Expenditures" in M12833

Matter: Nova Scotia Power Inc. - Decarbonization Deferral Account (DDA) -  2025 Annual Report
5 passages 5 documents

Capital Expenditures across all matters →

N-2NSPI (CA) RIR 1 to 2 1 passage
8
8 Plant Forecast Retirement Date (End of) Forecast Decommissioning Costs (Inflation Adj.) Cumulative Accretion Unrecovered Forecast Decommissioning Costs Point Aconi 2029 35.5 11.5 24.0 PTMT 2029 9.0 4.7 4.3 INP 2029 19.7 - 19.7 Trenton 20...

AI summary The table provides a forecast of plant retirement dates and decommissioning costs for various facilities, including cumulative accretion and unrecovered costs. The data includes Aconi, PTMT, INP, and Trenton, with total decommissioning costs estimated at $107.5 million.

N-4NSPI (NSEB) RIR 1 to 5 1 passage
NON-CONFIDENTIAL
NON-CONFIDENTIAL Request IR-3: Reference: Appendix B Please provide further detail on the necessity for the increased spending on the turbine, boiler and ash site at Point Aconi (as noted in response to IR-12 in M12742) resulting in additi...

AI summary The increased spending of $24.5 million at Point Aconi in 2025 compared to the previous forecast of $16.4 million was due to findings during a planned outage in Q4 2025. Additional refurbishment and component replacement were required after inspections revealed as-found conditions that necessitated further investment to ensure safe and reliable operations until the unit's retirement in 2029.

102151NSEB (NSPI) IR 1 to 5 1 passage
Request IR-3:
Request IR-3: - Reference: Appendix B - Please provide further detail on the necessity for the increased spending on the turbine, boiler - and ash site at Point Aconi (as noted in response to IR-12 in M12742) resulting in additions of - $2...

AI summary The text requests detailed justification for increased capital expenditures at Point Aconi's turbine, boiler, and ash site, citing a $24.5 million increase in 2025 compared to the previous $16.4 million forecast, referencing prior response IR-12 in M12742.

102199CA (NSPI) IR-1 to IR-2 1 passage
Section 2
1 Request IR-1: 2 Reference: Figure 2 – Unrecovered DDA costs in 2029 assuming 2026 Securitization. 3 4 1. Please provide an explanation for the expenses included for each unit/plant in the 5 "remaining NBV" column. 6 7 2. Please provide a...

AI summary The document contains two requests (IR-1 and IR-2) related to the unrecovered DDA costs in 2029 under the assumption of a 2026 securitization. The requests seek explanations for the expenses in the 'remaining NBV' column, the derivation of decommissioning cost forecasts, the impact of delaying securitization to 2027, and the possibility of including these costs in the securitization approach.

102942Replys Submission - NSPI 1 passage
Preamble p. p. 5
e Company will work with its capital market advisors 30 and propose to include additional incurred costs in the transaction if doing so continued to provide DATE FILED: July 24, 2026 Page 5 of 8

AI summary The document mentions a company planning to work with its capital market advisors to include additional incurred costs in a transaction if it continues to provide value.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →