Topic/Matter Intersection

Topic:"Capital Expenditures" in M12837

Matter: Nova Scotia Power Inc. - CI C0061552 – L6043 Replacements and Upgrades- $3,603,3512026 Q1 Capital Reports
9 passages 3 documents

Capital Expenditures across all matters →

N-1CI C0061552 – L6043 Replacements and Upgrades- $3,603,351 2 passages
NSEB APPROVAL SHEET p. p. 1
NSEB APPROVAL SHEET Project Title: L6043 Replacements and Upgrades CI Number: C0061552 Date: May 4, 2026 Expenditure Profile Type of Filing Year Budget Amount Project Estimate Capital Project Authorization Unforeseen and Unbudgeted (U&U) P...

AI summary The document outlines a capital project authorization for the L6043 Replacements and Upgrades project, including budget amounts, project estimates, and authorization details for 2026 and 2027. It includes comments and is signed by an authorized signatory.

Execution Year: 2026-2027 p. p. 1
Execution Year: 2026-2027 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour T&D Labour - Site Supervision Design - Engineering PD PD 60 220 $ $ 461 452 $ $ 27,79...

AI summary The document outlines a cost estimate for a project spanning 2026-2027, including labor, materials, contracts, and overhead costs. It breaks down expenses into categories such as regular labor, materials, contracts, and administrative overhead, with a total estimated cost of $3,603,351.

N-2NSPI (NSEB) RIRs 1-5 2 passages
Execution Year: 2026
Execution Year: 2026 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Sub-Total $ 131,506 Materials Sub-Total $ 356,744 Contracts Sub-Total $ 1,385,505 Other Go...

AI summary The document provides a cost estimate breakdown for a project in 2026, including categories such as labour, materials, contracts, and contingency. The total estimated cost is $2,154,819, with contingency accounting for 15% of the total. The figures are used for budgeting purposes and include an average of salaries across various job classifications.

NON-CONFIDENTIAL
NON-CONFIDENTIAL Request IR-2: - Please explain how the lot Unit Estimates for Wood Poles, Insulators, and O/H Conductors - under each of "Materials' and "Contracts" were calculated and explain any differences in - unit prices used for the...

AI summary The response explains how unit estimates for materials and contracts were calculated for wood poles, insulators, and O/H conductors. Material costs are based on NS Power's Compatible Unit (CU) estimates, while contract costs are based on contractor CU rates for installation and replacement.

101860Letter NSPI re:First Quarter 2026 Capital Items 5 passages
Preamble p. p. 0
May 4, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: First Quarter 2026 Capital Items Dear Ms. Henwood: Enclosed for your review and approval are the following c...

AI summary A letter dated May 4, 2026, addressed to Crystal Henwood, Clerk of the Nova Scotia Energy Board, requesting approval of capital items for the first quarter of 2026. The document encloses unspecified capital items for review and approval by the board.

2026 ACE Plan Capital Items for Subsequent Approval p. p. 0
2026 ACE Plan Capital Items for Subsequent Approval - CI C0061552 L6043 Replacements and Upgrades- $3,603,351 2026 ACE amount $2,457,629 $0 spent as at December 31, 2025 Non-Confidential - CI C0082133 IT-Renew Microsoft Enterprise Agreemen...

AI summary The document lists three capital items under the 2026 ACE Plan awaiting approval, including equipment upgrades, IT renewals, and infrastructure refurbishments, with specified funding amounts and confidentiality status. No expenditures have been made as of December 31, 2025.

Unforeseen & Unbudgeted (U&U) Capital Items p. p. 0
Unforeseen & Unbudgeted (U&U) Capital Items • CI C0080150 – TUC1 HP Turbine Refurbishment - $2,527,606 $2,527,606 spent as at December 31, 2025 Partially Confidential - CI C0083589 IR751 Brooklyn Community Solar $0 $0 spent as at December...

AI summary The document lists two Unforeseen & Unbudgeted (U&U) capital items: a fully spent turbine refurbishment project and two community solar projects with no expenditures as of December 31, 2025. All entries are marked as partially confidential.

Planned & Advanced (P&A) Capital Items p. p. 0
Planned & Advanced (P&A) Capital Items • CI C0044172 – L7005 Canso Crossing Vibration Mitigation - $2,431,095 $2,431,095 spent as at December 31, 2025 Partially Confidential

AI summary The document lists a completed capital project, CI C0044172 – L7005 Canso Crossing Vibration Mitigation, with total expenditures of $2,431,095 as of December 31, 2025. The item is marked as partially confidential.

Capital Reports p. p. 0
Capital Reports NS Power is working to compile its Q1 capital reports, and expects to file them in the coming weeks.

AI summary NS Power is preparing its Q1 capital reports and anticipates filing them in the near future. The text highlights the organization's current activity related to capital reporting obligations.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →