N-1CI C0083591 – IR746 Petpeswick Community Solar - $0 - Redacted
6 passages
REDACTED (CONFIDENTIAL INFORMATION REMOVED) CI C0083591 IR746 Petpeswick Community Solar REDACTED May 4, 2026 REDACTED (CONFIDENTIAL INFORMATION REMOVED) NSEB APPROVAL SHEET Project Title: IR746 Petpeswick Community Solar CI Number: C00835...
AI summary This document is an NSEB approval sheet for the IR746 Petpeswick Community Solar project, detailing expenditure profiles and approvals. It includes budget amounts, project estimates, and authorization types for the years 2026 and 2027. The document was submitted by Nova Scotia Power Incorporated and approved by the Nova Scotia Energy Board on May 4, 2026.
DESCRIPTION: In order to accommodate the new Petpeswick Community Solar generation project, NS Power must undertake upgrades to and expansion of existing distribution facilities (at the Interconnection Customer's expense). The required wor...
AI summary NS Power must upgrade distribution facilities for the Petpeswick Community Solar project, with costs borne by the Interconnection Customer, based on the Final Distribution System Impact Study (DSIS) for IR746.
Execution Year: 2026-2027 Cost Support Completed Similar Description Unit Quantity Unit Estimate Total Estimate Reference Projects (FP#'s) Regular Labour Electrician PD 750 $ 403 $ 302,461 Engineering PD 51 $ 452 $ 22,844 Sub-Total $ 325,3...
AI summary The document outlines a cost breakdown for a project with execution years 2026-2027, including labor, travel, materials, and overhead costs. It provides estimates for various components such as electrician labor, engineering, travel expenses, and materials like metering racks and communication modems. The table also includes capital contributions and administrative overhead.
SUMMARY This study was initiated to determine the requirements and conditions for the proposed interconnection of 2.2 MW of solar generation with inverters by the Interconnection Customer (IC) at the West Petpeswick Road, Musquodoboit Harb...
AI summary This report outlines the interconnection requirements for a 2.2 MW solar farm in Musquodoboit Harbour, Nova Scotia. Alternative C was selected after evaluation, requiring a gang-operated switch and NSPI to upgrade distribution facilities at the Interconnection Customer's expense. Key responsibilities include the IC covering line extensions, right-of-way acquisition, and maintenance costs.
REDACTED CI C0083591 Attachment 1 Page 3 of 39 REDACTED (CONFIDENTIAL INFORMATION REMOVED) guy replacements, and customer owned equipment such as the gang-operated switch is not included in these estimates. - The cost estimate to complete...
AI summary The document outlines interconnection requirements for a solar project, including a $1,062,874 cost estimate, compliance with NSPI standards, flicker emission management, power factor specifications, and electrical safety protocols. NSPI retains operational control over high-voltage equipment and may disconnect the facility if flicker issues persist. The Interconnection Customer must adhere to electrical codes and obtain permits.
REDACTED CI C0083591 Attachment 1 Page 22 of 39 REDACTED (CONFIDENTIAL INFORMATION REMOVED) - Electronic recloser complete with internal PTs; a remote protection cabinet; and electronic controller must be installed at the Point of Intercon...
AI summary The document outlines requirements for installing electronic recloser equipment with PTs, a remote protection cabinet, and an electronic controller at the Point of Interconnection, including a procurement security cost of $95,850+ HST and a 12-month lead time for Primary Metering.
101855Letter NSPI re:First Quarter 2026 Capital Items
5 passages
May 4, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: First Quarter 2026 Capital Items Dear Ms. Henwood: Enclosed for your review and approval are the following c...
AI summary A letter dated May 4, 2026, addresses Crystal Henwood, Clerk of the Nova Scotia Energy Board, submitting capital items for first-quarter 2026 review and approval. The document lacks detailed content beyond the submission request.
2026 ACE Plan Capital Items for Subsequent Approval - CI C0061552 L6043 Replacements and Upgrades- $3,603,351 2026 ACE amount $2,457,629 $0 spent as at December 31, 2025 Non-Confidential - CI C0082133 IT-Renew Microsoft Enterprise Agreemen...
AI summary The 2026 ACE Plan lists capital expenditure items requiring approval, including project-specific costs and funding allocations. Each entry details project identifiers, descriptions, budgeted amounts, and spending status as of December 31, 2025, with some items marked as partially confidential.
Unforeseen & Unbudgeted (U&U) Capital Items • CI C0080150 – TUC1 HP Turbine Refurbishment - $2,527,606 $2,527,606 spent as at December 31, 2025 Partially Confidential - CI C0083589 IR751 Brooklyn Community Solar $0 $0 spent as at December...
AI summary The document lists two Unforeseen & Unbudgeted (U&U) capital items: a fully spent turbine refurbishment (CI C0080150) and two unfunded community solar projects (CI C0083589, CI C0083591), all marked as partially confidential as of December 31, 2025.
Planned & Advanced (P&A) Capital Items • CI C0044172 – L7005 Canso Crossing Vibration Mitigation - $2,431,095 $2,431,095 spent as at December 31, 2025 Partially Confidential
AI summary The document details the completion of the L7005 Canso Crossing Vibration Mitigation project under CI C0044172, with total expenditures of $2,431,095 fully incurred by December 31, 2025. The item is marked as partially confidential.
Capital Reports NS Power is working to compile its Q1 capital reports, and expects to file them in the coming weeks.
AI summary NS Power is in the process of compiling its first-quarter capital reports and anticipates filing them in the near future as part of regulatory proceedings.