Topic/Matter Intersection

Topic:"Capital Expenditures" in M12914

Matter: NSP Maritime Link Inc. -  2027 / 2028 Assessment Application - NSPML
17 passages 5 documents

Capital Expenditures across all matters →

N-1Application - Redacted 12 passages
1 1.0 INTRODUCTION
1 1.0 INTRODUCTION 2 3 NSP Maritime Link Incorporated (NSPML, Company) makes this Application for 4 approval of an assessment from Nova Scotia Power Incorporated (NS Power) for 5 recovery by NSPML of its 2027 and 2028 revenue requirements....

AI summary NSP Maritime Link Incorporated (NSPML) is seeking approval to recover its 2027 and 2028 revenue requirements, totaling $200.3 million and $191.5 million respectively. The request includes operating and maintenance costs, depreciation, interest, and financing costs, with adjustments to debt and equity financing costs and inflationary impacts. NSPML also proposes an alternate approach for the 2027 marine survey due to its materiality and prudence for customers.

Preamble
10 11 12 13 14 15 As has been the case since 2018, NSPML will continue to invoice NS Power for recovery of its approved 2027 and 2028 assessments in equal monthly instalments ($13.46 million per month for 2027, and $12.79 million per month...

AI summary NSPML will continue to invoice NS Power for the recovery of its approved 2027 and 2028 assessments in equal monthly instalments, with specific adjustments for FLG2 costs and marine survey costs. The depreciation costs are increasing due to the full-year expense of the rock protection campaign in 2027 and the implementation of the station control monitoring system update in 2028.

3 2.3.1 Original Capital Costs
3 2.3.1 Original Capital Costs 4 5 In the Final Project Costs Decision (M10206), the NSEB approved NSPML's 6 depreciation policy as developed from the depreciation study conducted by Gannett 7 Fleming. This policy is built on the overridin...

AI summary The NSEB approved NSPML's depreciation policy based on a 2021 study by Gannett Fleming. NSPML plans to update the study within six months of completing the Cable Protection Project in Q3 2026, following a recommendation from Grant Thornton in the 2025 Assessment Decision.

21 2.3.2 Sustaining Capital
21 2.3.2 Sustaining Capital 22 23 NSPML anticipates that it will incur capital expenditures in 2027 of $0.5 million for 24 routine capital expenditures and $ in 2028. $ (pending 25 application and approval) in 2028 relates to upgrades to t...

AI summary NSPML anticipates capital expenditures of $0.5 million in 2027 and additional costs in 2028 for the Station Control Monitoring System (SCM) upgrade. Routine capital expenditures are being sought for approval in this Application, while a separate application will be filed for the full project costs due to exceeding the $1 million threshold.

Table 3 Capital Initiatives Comments 2027 2028 (Amounts in $millions) Recurring, smaller expenditures including Routine Capital 0.5 1.5 any maintenance, repairs, alterations, & Routine Spares improvements, replacements, renewals and additions. The increase in 2028 from 2027 primarily relates to purchase of IGBT spares. Station Control Monitoring System Total 0.5
Table 3 Capital Initiatives Comments 2027 2028 (Amounts in $millions) Recurring, smaller expenditures including Routine Capital 0.5 1.5 any maintenance, repairs, alterations, & Routine Spares improvements, replacements, renewals and additi...

AI summary Table 3 outlines capital initiatives for 2027 and 2028, highlighting recurring expenditures such as maintenance, repairs, and replacements. The increase in 2028 is attributed to the purchase of IGBT spares, with a total of $0.5 million allocated for the Station Control Monitoring System.

2.3.3 Capital Depreciation
2.3.3 Capital Depreciation 12 13 14 15 16 17 11 Consistent with the Final Costs Decision and its approved depreciation policy, NSPML seeks to recover $57.7 million in depreciation in 2027 and $58.1 million in 2028 which is calculated in ac...

AI summary NSPML seeks to recover $57.7 million in depreciation in 2027 and $58.1 million in 2028, consistent with the Final Costs Decision. The increase in 2027 is due to the Cable Protection Project, and the increase in 2028 is due to the SCM upgrade. Adjustments from close-out matters are not expected to have a material impact.

12 2.4.1 Annual Net Interest Costs
12 2.4.1 Annual Net Interest Costs 13 14 The requested recovery of annual net interest costs in 2027 is $36.7 million. This 15 represents total coupon interest costs of $36.1 million, letter of credit fees of $0.4 16 million, interest on d...

AI summary The document discusses the requested recovery of annual net interest costs for 2027 and 2028, including coupon interest, letter of credit fees, and interest on debt financing, partially offset by interest revenue and disallowed expenses. It also outlines the financing structure for the Maritime Link project, including bond guarantees and repayment schedules.

15 Key considerations include:
15 Key considerations include: 16 17 NSPML's borrowing rates are higher than NS Power's due to the absence of a credit 18 rating and the pledging of all assets under FLG and FLG2. 19 Based on NSPML's understanding of the traditional applic...

AI summary NSPML faces higher borrowing rates due to the absence of a credit rating and asset pledging under FLG and FLG2. Smoothing mechanisms may lead to adverse WACC impacts for customers, and NSPML lacks a balancing mechanism like FAM, complicating debt-to-equity ratio management. NSPML would comply with smoothing if directed by the Board but requests flexibility to adjust DER impacts and revisit the approach if needed.

1 5.0 ASSET MANAGEMENT OUTLOOK
1 5.0 ASSET MANAGEMENT OUTLOOK 2 3 Similar to NSPML's update in the 2026 Assessment Application, material near to midterm expenditures continue to be the Cable Protection Project23 4 and updating or 5 replacement of HVDC station controls....

AI summary The document discusses the asset management outlook for the Maritime Link, highlighting planned sustaining capital projects and maintenance activities. It notes that the Maritime Link has been in service since 2018 and outlines the need for periodic capital expenditures due to factors like obsolescence and performance degradation.

24 5.1 Five Year Outlook - Planned Sustaining Capital Projects (2027-2032)
24 5.1 Five Year Outlook - Planned Sustaining Capital Projects (2027-2032) 25 26 There are two material sustaining capital initiatves in progress and under development 27 in the near term; the first is the Submarine Cable Protection Projec...

AI summary The document outlines two major sustaining capital initiatives: the Submarine Cable Protection Project and the replacement of the Station Control Monitoring system. Other sustaining capital requirements are expected to be routine over the 2027-2032 period.

23 NSPML Cable Protection Project (M12285).
23 NSPML Cable Protection Project (M12285). 1 5.2 2026 Submarine Cable Protection Project 2 3 NSPML received approval by the NSEB of this initiative under Board Matter number 4 M12285 in Q4 2025. A portion of the work was accelerated from...

AI summary NSPML received approval for the 2026 Submarine Cable Protection Project under Board Matter M12285 in Q4 2025. Some work was accelerated into 2025 due to vessel availability, with the remaining scope expected to be completed in Q3 2026. The project is currently within budget. Additionally, NSPML plans to update the Station Control and Monitoring (SCM) system in 2028 due to obsolescence, with further details to be submitted in a future capital application.

1 5.4 Routine – General
1 5.4 Routine – General 2 3 NSPML's routine capital program is for recurring annual expenditures of like-for-like 4 replacement of small pieces of equipment, upgrades or restoration to property and other 5 small additions as required. The...

AI summary NSPML's routine capital program involves annual expenditures for replacing and upgrading small equipment and property, with an estimated annual budget of $0.5 million. The exact amount may vary each year based on operational needs.

N-4NSPML (IG) RIRs 1-17 - Redacted 2 passages
Section 30 p. pp. 1-28
Based on the information in Attachment 1 from a Tier 1 Canadian national bank[1](#page-28-0) , NSPML's estimated incremental cost of borrowing relative to NS Power under current market conditions is in the range of CORRA + CSA + 170 bps to...

AI summary The document discusses NSPML's estimated incremental borrowing costs relative to NS Power, highlighting structural differences in their credit profiles, including subordination of assets and lower equity cushion. These factors increase NSPML's credit risk and borrowing costs compared to NS Power.

NSPML Responses to Industrial Group Information Requests p. p. 28
NSPML Responses to Industrial Group Information Requests 2 determine an alternative path to resolution. 3 4 Claims: 5 There are two outstanding land claims; NSPML is working with external counsel to resolve 6 these. 7 8 In total, the outst...

AI summary NSPML has responded to industrial group information requests regarding land claims, project costs, and credit facilities. The outstanding project costs are expected to be no more than $6 million, and the marine survey cost was treated as an O&M expense. NSPML has committed to a $25 million credit facility and an uncommitted accordion of $10 million, with questions raised about borrowing limits and expansion plans.

102962NSEB (NSPML) IR 1 to 12 1 passage
9 Request IR-5:
9 Request IR-5: - 10 Reference: Section 2.3.2 Sustaining Capital - 11 NSPML expects to incur capital expenditures in 2027 of $0.5 million and $1.5 m in 2028 for routine - 12 capital expenditures. - 13 a) Please provide NSPML's definition o...

AI summary NSPML is expected to incur routine capital expenditures of $0.5 million in 2027 and $1.5 million in 2028. The request asks for NSPML's definition of routine capital expenditures, the expenditure categories under General, and how NSPML forecasts these expenditures.

102966CA (NSPML) IR 1 to 7 1 passage
1 Request IR-6:
1 Request IR-6: 2 3 With respect to Exhibit N-1, p. 14-15, 16 and 24, NSPML requests approval for an estimated 4 depreciation associated with the SCM upgrades scheduled for September 2028. 5 6 (a) Please provide the forecast dates for the...

AI summary NSPML requests approval for depreciation costs related to SCM upgrades scheduled for 2028. The request includes questions about project timelines, filing schedules, justification for rate inclusion, and alternative cost recovery methods if depreciation is not approved.

102976IG (NSPML) IR 1 to 17 - Redacted 1 passage
23
23 1 Request IR-12: 2 Reference: Section 2.3.2, Sustaining Capital — Station Control Monitoring System (SCM) 3 (pp. 14–15, 24). 4 Preamble: The Application includes in 2028 for SCM depreciation based on 5 an original OEM quote of , but sta...

AI summary The text outlines regulatory requests related to depreciation and capital applications for the Station Control Monitoring System (SCM) upgrade and marine survey costs. It includes inquiries about timelines, documentation, and the treatment of costs in the rate base continuity schedule.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →