Maritime Launch Services REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) CI C0086325 October 5, 2026 REDACTED (CONFIDENTIAL INFORMATION REMOVED) NSEB APPROVAL SHEET Project Title: Maritime Launch Services CI Number: C0086325 Date: Oct...
AI summary The document is an NSEB approval sheet for the Maritime Launch Services project, submitted by Nova Scotia Power Incorporated. It includes a budget and expenditure profile for the years 2026 and 2027, with a capital project authorization and details of the approval process.
Execution Year: 2026-2027 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Scoping Planner PD 20 $ 414 $ 8,427 Engineering PD 11 $ 461 $ 4,889 On Site Superviso...
AI summary The document outlines cost estimates for a project spanning 2026-2027, including labor, materials, contracts, and administrative overhead. It provides a detailed breakdown of various costs, such as labor for planning, engineering, and supervision, as well as material costs for wood poles, overhead conductor, and other components.
REDACTED CI C0086325 Attachment 1 Page 19 of 23 REDACTED (CONFIDENTIAL INFORMATION REMOVED) MLS Spaceport – 3 MVA Load Impact Study The Utility Service Requirements can be accessed on [www.nspower.ca](http://www.nspower.ca/) under Electric...
AI summary The document outlines the process for determining required network upgrades based on a load impact study and specifies that the load customer must contribute to the cost of upgrades, except when justified by NSPI's board-approved Capital Expenditure Justification Criteria.
Estimate 1 Purchase and install electronic recloser and control $75,000 2 Extend 24C-442 4.7 kilometers (approx.) from the Town of Canso to the MLS site using 336 ASC conductor $4,000,000 3 Purchase and install set of 200 Amp 25 kV voltage...
AI summary The document outlines various infrastructure projects with associated costs, including the purchase and installation of electrical equipment and the extension of power lines. It also references a section discussing the lead time to implement circuit modifications.