3.2 UPDATES TO AVOIDED COST CALCULATION In its decision approving the 2023-2025 DSM Plan, the NSUARB (as it then was) made note of the fact that updates to NS Power Integrated Resource Planning process will have an impact on the avoided co...
AI summary The NSUARB directed E1 to update avoided cost calculations for DSM plans using the latest IRP data, noting climate goals are not fully addressed in current IRP versions. E1 incorporated 2022 IRP results, embedding carbon costs into energy avoided costs for the 2026 DSM Extension. The DSMAG will address climate-related updates for future plans, while the More Access to Energy Act mandates IESO's IRP process.