1 Request IR – 7 - 2 Refer to the 2026 Report Section 3 Existing Generation Resources, page 9, footnote 9. Please - 3 describe how much of the installed capacity in Table 2 is attributable to the Community Feed-In- - 4 Tariff (FIT) program...
AI summary The response to Request IR–7 indicates that 2.5 MW of the 27.6 MW of Biomass IPP capacity is attributable to the Community Feed-In-Tariff (FIT) program. Biogas FIT projects were aggregated with biomass projects due to their small volume. A list of all FIT projects is available in the 2025 Comfit Annual Report (M12687).