Topic/Matter Intersection

Topic:"Compliance Legislation" in M03632

Matter: BRD-E-R-10 - Renewable Energy Community Feed-in Tariffs (COMFIT)see also M04523
14 passages 12 documents

Compliance Legislation across all matters →

B-9Evidence filed by Kwilmu'kw Maw-klusuaqn (KMKNO) 3/18/2011 1 passage
Legislation for Financial Institutions in Canada p. p. 19
Legislation for Financial Institutions in Canada There are also several pieces of legislation that are specific to the financial services industry that have to be considered in developing the structure of an Aboriginal financial services i...

AI summary This text outlines the legislative and regulatory framework governing financial institutions in Canada, particularly for Aboriginal groups. It highlights key legislation such as The Bank Act, The Trust and Loan Companies Act, and compliance requirements enforced by OSFI. The discussion emphasizes the complexity of starting a bank or trust company and the importance of meeting capital and liquidity requirements.

B-11Evidence of Alliance of Nova Scotia Sawmillers 3/22/2011 1 passage
Q. Do you think this labour requirement is reasonable? p. p. 138
Q. Do you think this labour requirement is reasonable? A. It seems excessive given the size of the plant. The requirement for 24 hour supervision of the plant puts a significant labour cost burden on rate payers for plants of this scale. W...

AI summary The respondent argues that the 24-hour supervision labour requirement for the COMFIT plant is excessive and places an undue financial burden on rate payers. They suggest that the Department of Labour & Safety should review whether reduced supervision could safely operate the plant, similar to how heating boilers are managed.

07337Board Decision 2 passages
8.2 Findings p. p. 0
8.2 Findings [130] With respect to the capacity factor, Synapse proposed a rate of 23%. The Board considers Seaforth's comments to be reasonable in terms of supporting the 23% recommendation. Based on its review of the evidence, the Board...

AI summary The Board accepts Seaforth's support for a 23% capacity factor for small wind projects. It adjusts Synapse's interconnection cost from $13,300 to $21,550 based on evidence from Scotian WindFields. The Board also increases Routine O&M costs from $1,642 to $4,500 annually, citing evidence from small wind operators. These changes are to be addressed in the Compliance Filing.

14.0 SUMMARY p. p. 0
an annual report with the Board by January 31 st each year which provides a listing of, and details regarding, each COMFIT generator that is at any stage of the application or interconnection process. [290] The Board directs Synapse to pro...

AI summary The Board requires Synapse to submit revised FIT model calculations and draft terms and conditions for tariffs. An annual report detailing COMFIT generators is also mandated.

07604Compliance Filing 8/2/2011 1 passage
Ope ratin Yea g r
Nova Scotia COMFIT Model Depreciation Worksheet: Bottom Synapse Compliance Large Wind, Taxable Owner Ope ratin Yea g r 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 40-y r SL 2.50 % 2.50 % 2.50 % 2.50 % 2.50 % 2.50 % 2.50 % 2.50 % 2...

AI summary The document presents a depreciation worksheet for a wind energy project in Nova Scotia, showing a 40-year straight-line depreciation rate of 2.50% annually. It is part of the COMFIT model used for financial compliance and taxation purposes.

U-2 - Spreadsheet Showing the Offsetting Adjustment to Calculations in the Biomass CHP Tariff06750 4/14/2011 1 passage
Nova Scotia COMFIT Model Biomass CHP (condensing turbine; new b
4/12/11 Exhibit K with corrected heat content of steam Nova Scotia COMFIT Model Biomass CHP (condensing turbine; new b

AI summary The text presents an exhibit related to the Nova Scotia COMFIT Model, specifically concerning a Biomass CHP (condensing turbine; new b) with a corrected heat content of steam. The exhibit appears to be part of a regulatory proceeding.

U-8 - Synapse Model Using Neal Livingston's Assumptions - Pynn Letter and Payback in 10 years06756 4/14/2011 1 passage
Nova Scotia COMFIT Model Large Wind (Over 50 kW) Synapse U-8
Nova Scotia COMFIT Model Large Wind (Over 50 kW) Synapse U-8 Development Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Secondary Second...

AI summary The document presents the Nova Scotia COMFIT Model for Large Wind (Over 50 kW) Synapse U-8, which includes a table with multiple 'Secondary' entries and notes about assumptions. The content primarily focuses on modeling and assumptions related to wind energy forecasting and impact tracking.

06888Ecology Action Centre Reply Submission 5/6/2011 1 passage
Section 3 p. pp. 0-1
Therefore, given the lack of substantive participation on the part of the Government, and, the powers granted to the Board within the Public Utilities Act, the Ecology Action Centre suggests that it is well within the scope and mandate of...

AI summary The Ecology Action Centre argues that the Board has the authority to set multiple wind tariffs using linear interpolation and to interpret COMFIT ratesetting in the public interest, despite outstanding issues with COMFIT. They also suggest that higher-level policy changes are needed to support electricity market restructuring and achieve sustainable prosperity goals.

07337Board Decision 1 passage
14.0 SUMMARY p. p. 0
an annual report with the Board by January 31 st each year which provides a listing of, and details regarding, each COMFIT generator that is at any stage of the application or interconnection process. [290] The Board directs Synapse to pro...

AI summary The Board requires Synapse to submit revised FIT model calculations and draft tariff terms and conditions as part of a compliance filing. This directive follows the submission of an annual report by January 31st, detailing COMFIT generators at various stages of application or interconnection.

07621Comments on Compliance Filing by ANSS 8/5/2011 1 passage
VIA EMAIL p. p. 0
VIA EMAIL Nancy McNeil Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 3rd Floor 1601 Lower Water Street PO Box 1692 Unit "M" Halifax NS B3J 383 Nancy G. Rubin Direct Dial: 902.420.3337 [email protected] Dear...

AI summary The Alliance of Nova Scotia Sawmillers (ANSS) submits comments regarding the Community Feed In Tariff (COMFIT) compliance filing. They request that the draft COMFIT terms include additional wording reflecting the Board's decision on the fuel escalator for biomass CHP projects and note an oversight in the Synapse compliance spreadsheet regarding parasitic power.

20110405-1Hearing Transcript — 4/5/2011 (Synapse Panel, ANSS Panel) 1 passage
- DICTUM DIGITAL INC. CERTIFIED COURT REPORTERS set by the Board; is that possible the way you see it?
- DICTUM DIGITAL INC. CERTIFIED COURT REPORTERS set by the Board; is that possible the way you see it? 1 NSUARB-BRD-E-R.10 Page 549 MR. TRAVIS: Well, no. I mean, we 14 That all by itself does not benefit ratepayers. It only 15 benefits rat...

AI summary The discussion highlights the importance of cost-based rates for ratepayer benefits from energy efficiency, and mentions the exemption of certain sectors from COMFIT rules, with the forestry industry and related companies being specifically referenced.

20110406-1Hearing Transcript — 4/6/2011 (ANSS Panel, St. Francis Xavier Univ, Consumer Adv. Panel) 1 passage
- be.
- be. Page 750 NSUARB-BRD-E-R.10 8 to debt in the building of buildings and those types of 9 things. And traditionally that's their approach has 10 been to accumulate the funds and make the investments. 11 Under the COMFIT we're of the vie...

AI summary The text discusses participation in COMFIT by a university or as a commodity power developer, with various ownership possibilities. It includes a mention of a court reporter and page numbers from a regulatory proceeding document.

20110407-1Hearing Transcript — 4/7/2011 (Consumer Adv. Panel, Cdn. Wind Energy Panel, EAC - T. Couture) 2 passages
report back.
report back. 1 If NSPI is prepared to undertake to 2 produce it, that would be the more direct way, I would 3 think. 4 THE CHAIR: Why don't you and 5 Ms. Godbout chat about it and see how we might most 6 effectively do it? NSPI hasn't prod...

AI summary The discussion revolves around NSPI's production of a witness and confidentiality concerns, as well as a question about community eligibility requirements for feed-in tariffs in other jurisdictions, specifically referencing Ontario's provisions.

- percent.
- percent. NSUARB-BRD-E-R.10 Page 1029 12 and a Hatch Study is an analysis of wind speeds, not of 13 historical data. 14 MR. LIVINGSTON: And are you familiar 15 with the application form that was filled out by the 16 applicants relative to...

AI summary The discussion revolves around the source of information used to determine capacity factors for wind projects. Mr. Livingston questions Mr. Chernick about the origin of the data, and Mr. Chernick responds that it came from summaries provided by NSPI in compliance filings and updates to the Board.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →