Matter: Riverport Electric Light Commission Complaint - Power Poles - Martin and Wendy Tanner
1 passage 1 document

Compliance Legislation across all matters →

99194Board Decision Letter - Redacted 1 passage
CONCLUSION
CONCLUSION After reviewing all the evidence before the Board, including the Strum June Report, the Board is satisfied that RELC has addressed the clearance issues raised in your complaint. The vertical clearance and all horizontal clearanc...

AI summary The Board concludes that RELC has adequately addressed the clearance issues raised in the complaint, except for one non-compliant horizontal line clearance. The Board dismisses the complaint but directs RELC to review similar situations in the area to ensure safety and compliance with the Act.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →