N-4NSPML (IG) RIRs 1-26 - Redacted
5 passages
NSPML Responses to Industrial Group Information Requests 1 Request IR-01: 25 purposes of the relief available for the 12-month Compliance Period? 26 If not, identify the threshold that NSPML proposes the Board apply in 27 distinguishing qu...
AI summary NSPML responds to information requests regarding the definition of 'Good Utility Practice' and outage terminology, referencing the Lower Churchill Project Commercial Agreements, the Federal Loan Guarantee, and CIGRE TB 956. NSPML confirms it uses definitions from these sources in its commercial agreements.
5.17 Taxes. - 5.17.1 Interconnection Customer Payments Not Taxable. The Parties intend that all payments or property transfers made by Interconnection Customer to Transmission Provider for the installation of Transmission Provider's Interc...
AI summary The section outlines that payments by Interconnection Customer to Transmission Provider for interconnection facilities and network upgrades are non-taxable under IRS guidelines. It references IRS Notices 2001-82 and 88-129, requiring capitalization of costs as intangible assets over 20 years and limiting dual-use intertie power flows to 5% in the direction of the Large Generating Facility.
5.19 Modification. 5.19.1 General. Either Party may undertake modifications to its facilities. If a Party plans to undertake a modification that reasonably may be expected to affect the other Party's facilities, that Party shall provide to...
AI summary Section 5.19 outlines procedures for facility modifications under a JOA, requiring advance notice, confidentiality, and cost allocation rules. Modifications must comply with LGIA and Good Utility Practice. Interconnection Customer is not liable for Transmission Provider's modification costs but must cover their own necessary upgrades.
Article 9. Operations - 9.1 General. Each Party shall comply with the Electric Reliability Organization requirements. Each Party shall provide to the other Party all information that may reasonably be required by the other Party to comply...
AI summary Article 9 outlines operational compliance requirements, including adherence to Electric Reliability Organization standards and procedures for notifying the Balancing Authority Area for Large Generating Facilities. Parties must share necessary information and execute agreements prior to facility synchronization.
14.2 Governing Law. - 14.2.1 The validity, interpretation and performance of this LGIA and each of its provisions shall be governed by the laws of the state where the Point of Interconnection is located, without regard to its conflicts of...
AI summary Section 14.2 of the LGIA establishes that the agreement is governed by the laws of the state where the Point of Interconnection is located, subject to applicable laws and regulations. Parties retain the right to contest or appeal governmental laws, orders, or regulations.
101312IG (NSPML) IR 1 to 26 - Redacted
3 passages
11 Request IR-6: - 12 Reference: N-01 Application, Sections 3.0 and 4.0; and Appendix A. - 13 Preamble: The Application relies on the 12-month period from May 2023 to April 2024 - 14 as the "Compliance Period", during which NSPML asserts t...
AI summary Request IR-6 examines NSPML's compliance with the 90% Base Block energy threshold during May 2023–April 2024, noting deferred energy balance reductions by June 2024 and post-compliance period redelivery by December 2024. The request questions whether subsequent periods (May 2024–April 2025 and May 2025–March 2026) meet termination conditions, citing data gaps and non-compliance in five months (July–December 2024).
- 1 Request IR-15: - 2 Reference: N-01 Application, Section 6.0; and Appendix B. - 3 And Reference: Matter M11773, N-01 NSPML Holdback Mechanism Letter (June 28, - 4 2024). - 5 Preamble: Appendix B sets out holdback amounts since the Compl...
AI summary NSPML requests interest on deferred holdback funds, verification of financial figures, and a separate proceeding to design a continuing holdback mechanism. The Board questions NSPML's entitlement to interest, data sources, and calculation details, citing prior compliance period data and WACC rates.
28 was considered; 1 (iii) The nature of the work scope performed during the outage 28 affected equipment that were outstanding at the time of the 29 failure, including any items documented in commissioning 30 punch lists, failure investig...
AI summary The text discusses the evaluation of an unplanned outage, focusing on the nature of the work scope, design standards, compliance with CSA standards, and protective actions taken. It also requests documentation to support the determination of whether the outage falls within Good Utility Practice.
102699Submission - IG
3 passages
RELIEF FROM THE THRESHOLD REQUIREMENTS IS NOT WARRANTED The Board has allowed for a degree of flexibility for NSPML to meet the stated threshold obligations, to address the need for some margin of interruption that is " required due to goo...
AI summary The Board has not granted relief from threshold requirements for NSPML, emphasizing that relief is discretionary and must be justified by good utility practice or exceptional circumstances. The burden of proof was not met, and the evidence did not support the need for such relief.
July 2023 Outage NSPML seeks good utility practice relief for the five-day planned LIL bipole outage in July 2023, characterizing it as a post-commissioning software and SCADA update outage required to enhance reliability. Base NS Block de...
AI summary NSPML requests relief for a July 2023 outage, claiming it was necessary for post-commissioning software updates. The Industrial Group argues that the outage was not routine and did not meet good utility practice standards, as the work was deferred commissioning rather than routine maintenance. Software issues continued to affect the LIL's performance, and the final software was installed months after the compliance period.
CONCLUSION The Industrial Group respectfully requests that the Board: - 1. Reject NSPML's request to terminate the Holdback retroactively to May 2024 on the basis that: - (a) NSPML has not demonstrated full compliance with the Board's hold...
AI summary The Industrial Group requests the Board to reject NSPML's retroactive termination of the Holdback due to non-compliance with conditions and lack of justification for relief. Alternatively, if termination is granted, they argue that NSPML should not receive WACC on post-Compliance Period holdback amounts due to delays in the application.
102909Reply Submission - NSPML
5 passages
Date Filed: July 23, 2026 Page 4 of 44 1 Evidence supports relief for the four months during the proposed Compliance Period that 21 second Submission after reviewing Bates White's evidence and IR responses, and 22 NSPML's Rebuttal evidence...
AI summary The Commissioner's Application (CA) supports the findings and recommendations made by Mr. Wilson based on evidence reviewed, and encourages the NSEB to strongly consider the Application. The Company responds by referencing previously filed evidence to assist the Board in its decision-making.
In my opinion, these four events meet the Board's standard for relief as they represent good utility practice (events 1-3) or exceptional circumstances (event 4).[7](#page-7-0) Again, NSPML encourages the Board to give strong weight to the...
AI summary The Company argues that four events meet the Board's standard for relief, representing good utility practice or exceptional circumstances. It also submits that customers were not harmed during the Compliance Period and that Make-up Energy deliveries exceeded contracted amounts, fulfilling the 'Consistent Deliveries' threshold.
Industrial Group Submission, filed July 9, 2026, pages 3, 7, 11,13 and 14. NSPML response to SBA IR-5 provides post-Compliance Period data. 1 2.0 ARGUMENT 2 3 2.1 Post-Compliance Period Performance 4 5 The Industrial Group argues that the...
AI summary The Industrial Group argues that the Holdback should not be ended due to NSPML's post-Compliance Period performance, with energy deliveries below 90% of contracted amounts in five of six months. The Board previously set a 12-month Compliance Period requirement in 2023, based on NSPML's short-term strong performance following the LIL commissioning.
15 SBA Submission, July 9, 2026, page 5. 16 NSEB Decision M11009, October 4, 2023, paragraph 93. In addition, in setting the criteria to end the Holdback, it was well known that, due to the period of under-delivery prior to commissioning o...
AI summary NSPML argues that it has met the conditions to end the Holdback, pointing to the delivery of 100% of contracted energy, including Make-up Energy, and strong performance during critical winter months. It emphasizes that the Commercial Agreements do not require fixed delivery commitments and that the Holdback is no longer necessary as the original terms of the agreement have been fulfilled.
To date, any under delivered energy has been offset by timely deliveries of Make-up Energy. This is proven in Table 2 above. While not in evidence, NSPML can conform that through May 2026, Undelivered Energy has continued to be at or near...
AI summary The document discusses the timing of NSPML's application filing, noting that it was driven by legitimate factors such as resource constraints and the need for complete information from the Compliance Period. The delay was attributed to competing operational and regulatory obligations and the need to ensure all necessary information was in place.