REDACTED CI C0083591 Attachment 1 Page 3 of 39 REDACTED (CONFIDENTIAL INFORMATION REMOVED) guy replacements, and customer owned equipment such as the gang-operated switch is not included in these estimates. - The cost estimate to complete...
AI summary The document outlines interconnection requirements for a solar project, including a $1,062,874 cost estimate, compliance with NSPI standards, flicker emission management, power factor specifications, and electrical safety protocols. NSPI retains operational control over high-voltage equipment and may disconnect the facility if flicker issues persist. The Interconnection Customer must adhere to electrical codes and obtain permits.
REDACTED CI C0083591 Attachment 1 Page 26 of 39 REDACTED (CONFIDENTIAL INFORMATION REMOVED) • NSPI shall have sole operational control over all NSPI owned high voltage equipment at the Petpeswick Solar Site. Operational Control of the Inte...
AI summary NSPI retains sole operational control over its high-voltage equipment at the Petpeswick Solar Site, while the Interconnection Customer's equipment control is governed by the SSGIA. The Interconnection Customer must comply with electrical codes, obtain permits, and ensure inspections by NSPI's Electrical Inspection Authority, including CSA-certified equipment and adherence to the Canadian Electrical Code.
1.4.1 Mature Urban and Developing Urban Areas Generally mature urban and developing urban areas are all those areas where there is significant residential development. This will normally equate to cities, towns and villages and associated...
AI summary The section outlines requirements for pole lines in mature and developing urban areas, specifying that the right-of-way must be grubbed and seeded with herbaceous plants or have hardwood trees over 4.6 meters removed, complying with erosion and sediment control principles from ENV 4.01, Section 2.